Consider the following cash flows for two mutually exclusive investments: t=0 t=1 t=2 t=3 A ($1,312) $898 $543 $111 B ($1,033) $101 $234 $1,033 Given the cost of capital is 8% what is the internal rate of return of the better project 11.13% 15.51% 12.10% 9.03% 18.45%
A) 11.13%
Explanation: We will choose the better project on the basis of the NPV. The project having higher Npv will be chosen.
Project A
Using financial calculator to calculate Npv
Inputs: C0= -1,312
C1= 898. Frequency= 1
C2= 543,. Frequency= 1
C3= 111. Frequency= 1
I = 8%
Npv= compute
We get, Npv of project A as $73.13
Project B
Using financial calculator to calculate Npv
Inputs: C0= -1,033
C1= 101. Frequency= 1
C2= 234. Frequency= 1
C3= 1,033. Frequency= 1
I= 8%
Npv= compute
We get, Npv of the project as $81.165
As the Npv of the project B is higher , we should calculate the IRR of Project B.
IRR of Project B
Using financial calculator to calculate IRR
Inputs: C0= -1,033
C1= 101. Frequency= 1
C2= 234. Frequency= 1
C3= 1,033. Frequency= 1
Irr= compute
We get, IRR of the project as 11.13%
Get Answers For Free
Most questions answered within 1 hours.