Question

A project has the following cash flow. Year Costs Benefits 0 $10,000 0 1 $1,000 $5,000...

A project has the following cash flow.

Year

Costs

Benefits

0

$10,000

0

1

$1,000

$5,000

2

$1,000

$5,000

3

$2,000

$6,000

4

$2,0000

$3,000

Assuming a discount rate of 10%, estimate the following:

a)Net Present Value (NPV)

b)Discounted Benefit-Cost Ratio

c)Net discounted Benefit-Cost Ratio

d)Is the project feasible? Explain your answer

Homework Answers

Answer #1
Year Cost Benefit Cash Flows = Benefit - Cost
0 10000 0 -10000
1 1000 5000 4000
2 1000 5000 4000
3 2000 6000 4000
4 20000 3000 -17000

Discount rate = 10%

a)

= $ 4000 / (1.1)1 + $ 4000 / (1.1)2 + $ 4000 / (1.1)3 - $ 17000 / (1.1)4 - $ 10000

= - $ 11663

b) Discounted Benefit Cost Value = $ 4000 / (1.1)1 + $ 4000 / (1.1)2 + $ 4000 / (1.1)3 - $ 17000 / (1.1)4

= - $ 1663

= - $ 1663 / $ 10000

= - 0.16

c)

= - $ 11663 / $ 10000

= - 1.16

d) No, the project is not feasible as the NPV is less than 0 and will not add value to shareholders wealth

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Preform a benefit/cost analysis on the following project: Expected costs: $5,000 today, $5,000 a year from...
Preform a benefit/cost analysis on the following project: Expected costs: $5,000 today, $5,000 a year from today, and $5,000 two years from today Expected revenue: $6,000 five years from today, $7,000 seven years from today, and $8,000 ten years from today. Assume a 6% discount rate The Net Present Value (NPV) of the project The benefit/cost ratio Is the project worth undertaking?
A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000...
A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000 2 1,000 3 1,000 4 2,000 5 2,000 Assuming an interest rate of 10%, the project's simple payback period is most nearly _________. A. 2 years B. 4 years C. 6 years D. 5 years E. 7 years Using the information in Problem #3 and linear interpolation, the project's discounted payback period is most nearly ___________. A. 3.62 years B. 2.33 years C. 2.05...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
You are considering a project with the following set of cash flows: Cash flow 0 -5,500...
You are considering a project with the following set of cash flows: Cash flow 0 -5,500 1 2,000 2 3,000 3 1,000 4 2,000 a. What is the payback period of this project? If the pre-specified cut off is 3 years, should this project be accepted? b. What is the discounted payback period of this project? If the pre-specified cut off is 3 years, should this project be accepted? The discount rate is 10%.
Shannon Industries is considering a project which has the following cash flows: Year Cash Flow 0...
Shannon Industries is considering a project which has the following cash flows: Year Cash Flow 0 ? 1 $2,000 2    $3,000 3 $3,000 4 $1,500    The project has a payback period of 2 years. The firm’s cost of capital is 12 percent. What is    the project’s net present value? (round your answer to the nearest $1.) a. $ 570 b. $ 730 c. $2,266 d. $2,761 e. $3,766
Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year...
Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year 2 = $3,500; Year 3 = $1,500; Year 4 = $3,000; and Year 5 = $1,500. The company’s hurdle rate is 9.00%. For Project A, please calculate: 1) the discounted payback period; 2) the net present value; 3) the internal rate of return; and 4) the modified internal rate of return.
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$10,000 -$8,000 1 2,000 7,000 2 2,000 3,000 3 6,000 1,000 4 8,000 3,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
13) Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000;...
13) Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year 2 = $3,500; Year 3 = $1,500; Year 4 = $3,000; and Year 5 = $1,500. The company’s hurdle rate is 9.00%. For Project A, please calculate: 1) the discounted payback period; 2) the net present value; 3) the internal rate of return; and 4) the modified internal rate of return. (3 points)
A project costs $4,000. You expect the following cash flows from the project: Year Cash Flow...
A project costs $4,000. You expect the following cash flows from the project: Year Cash Flow 1 $2,000 2 $6,000 3 $4,000 4 $8,000 5 $9,000 If the required rate of return is 14%, what is the NPV of this project? Round your answer to two decimal places.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT