A project has the following cash flow.
Year |
Costs |
Benefits |
0 |
$10,000 |
0 |
1 |
$1,000 |
$5,000 |
2 |
$1,000 |
$5,000 |
3 |
$2,000 |
$6,000 |
4 |
$2,0000 |
$3,000 |
Assuming a discount rate of 10%, estimate the following:
a)Net Present Value (NPV)
b)Discounted Benefit-Cost Ratio
c)Net discounted Benefit-Cost Ratio
d)Is the project feasible? Explain your answer
Year | Cost | Benefit | Cash Flows = Benefit - Cost |
0 | 10000 | 0 | -10000 |
1 | 1000 | 5000 | 4000 |
2 | 1000 | 5000 | 4000 |
3 | 2000 | 6000 | 4000 |
4 | 20000 | 3000 | -17000 |
Discount rate = 10%
a)
= $ 4000 / (1.1)1 + $ 4000 / (1.1)2 + $ 4000 / (1.1)3 - $ 17000 / (1.1)4 - $ 10000
= - $ 11663
b) Discounted Benefit Cost Value = $ 4000 / (1.1)1 + $ 4000 / (1.1)2 + $ 4000 / (1.1)3 - $ 17000 / (1.1)4
= - $ 1663
= - $ 1663 / $ 10000
= - 0.16
c)
= - $ 11663 / $ 10000
= - 1.16
d) No, the project is not feasible as the NPV is less than 0 and will not add value to shareholders wealth
Get Answers For Free
Most questions answered within 1 hours.