Question

The project is estimated to be of 10 years duration. It involves setting up new machinery...

The project is estimated to be of 10 years duration. It involves setting up new machinery with an estimated cost of as much as Thai baht (THB) 375 million, including installation. This amount could be depreciated using the straight-line method (SLM) over a period of 10 years with a resale value of THB13.5 million. The project would require an initial working capital of THB 15.5 million. With the planned new capacity, the company would be able to produce 60,000 pieces of shirts each year for the next 10 years. In terms of pricing, each shirt can initially be sold at THB 900 a piece, which takes into account the target segment and competitor pricing. The project proposal incorporates an annual increase of 3% in the price of the shirt to compensate for inflationary impact.

With regards to the raw material costs and other expenses, the project estimated the following details: Raw material cost for manufacturing shirts at THB325 per shirt, slated to rise by 2.5% per annum on account of inflation. Other direct manufacturing costs at THB55 per shirt with an annual increase of 2.5% per annum on account of inflation. Selling, general, and administrative expenses (including employee expenses) at THB 24 million per annum, expected to increase by 6% each year. Depreciation expense on the basis of SLM. Tax rate was assumed to be 30%.

For funding of the expansion project, the promoters agreed to infuse 50% in the form of equity with the rest (50%) being financed from issue of new debt. Based on the current credit position and market scenario, new debt can be raised by the company at 12% per annum. Cost of equity was assumed to be 15%. The requisite discounting rate or weighted average cost of capital (WACC) for NPV and IRR calculations can now be calculated with the help of the above assumptions.

Demand Scenario Although the project proposal estimates maximum annual production of 240,000 shirts, Saurabh decided to do capital budgeting analysis under two demand scenarios: Optimistic and Expected.

The likely annual demand estimated under each scenario is as follows:

Annual demand
Optimistic 60,000
Expected 120,000

A. On the basis of the financial information given in the case, calculate the after-tax operating cash flows, NPV, and IRR under the Optimistic and Expected scenarios. Clearly specify the calculations required for the same.

B. Based on your analysis, as Boon Mee, what recommendation would you make on whether the company should undertake the project or not? Clearly specify the decision based on both the NPV technique as well as the IRR criterion.

Homework Answers

Answer #1

Discount rate for the project = WACC calculated as (cost of equity + after-tax cost of debt)/2 since equity and debt are equally weighted.

Discount rate = (15% + 12%*(1-30%))/2 = 11.70%

A). NPV & IRR calculation for optimistic demand of 60,000:

NPV & IRR for expected demand of 120,000:

B). Optimistic demand - NPV and IRR both are negative which means that it will be a loss making project so it should not be undertaken.

Expected demand - NPV is still negative which means the project is still loss making. IRR is positive but less than the discount rate so the project is loss making. It should not be undertaken.

Note: There appears to be some error in the question because optimistic demand cannot be less than expected demand. Please check the figures given in the question.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the optimistic-scenario forecast, the annual sales volume is 58,200 units, while the sale price is $150 per unit with a variable cost of...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the optimistic-scenario forecast, the annual sales volume is 63,000 units, while the sale price is $162 per unit with a variable cost of...
A manufacturing firm has set up a project for developing a new machine for one of...
A manufacturing firm has set up a project for developing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1 million, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its implementation cost exceed 1,425,000, the project will not meet the firm’s NPV hurdle....
Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing...
Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing facility in an area recently damaged by a hurricane. THSI will lease space in this facility to various agencies and groups providing relief services to the area. THSI estimates that this project will initially cost $5.23 million to setup and will generate $20 million in revenues during its first and only year in operation (paid in one year). Operating expenses are expected to total...
Howell Petroleum is considering a new project that complements its existing business. The machine required for...
Howell Petroleum is considering a new project that complements its existing business. The machine required for the project costs $3.82 million. The marketing department predicts that sales related to the project will be $2.52 million per year for the next four years, after which the market will cease to exist. The machine will be depreciated down to zero over its four-year economic life using the straight-line method. Cost of goods sold and operating expenses related to the project are predicted...
A mining company is considering a new project. Because the mine has received a permit, the...
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $10.66 million at Year 0 to mitigate the environmental Problem, but it would not be required to do so. Developing the mine (without mitigation) would cost $66 million, and the expected cash inflows would be $22 million per year for 5 years. If the...
123 Inc. is considering purchasing a new machine. The machine will cost $3,250,000. The machine will...
123 Inc. is considering purchasing a new machine. The machine will cost $3,250,000. The machine will be used for a project that lasts 3 years. The expected salvage of the machine at the end of the project is $800,000. The machine will be used to produce widgets. The marketing department has forecasted that the company will be able to sell 280,000 widgets per year. The marketing department believes that the company will be able to charge $22 per widget. The...
123 Inc. is considering purchasing a new machine. The machine will cost $3,250,000. The machine will...
123 Inc. is considering purchasing a new machine. The machine will cost $3,250,000. The machine will be used for a project that lasts 3 years. The expected salvage of the machine at the end of the project is $800,000. The machine will be used to produce widgets. The marketing department has forecasted that the company will be able to sell 280,000 widgets per year. The marketing department believes that the company will be able to charge $22 per widget. The...
A mining company is considering a new project. Because the mine has received a permit, the...
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $11 million at Year 0 to mitigate the environmental Problem, but it would not be required to do so. Developing the mine (without mitigation) would cost $69 million, and the expected cash inflows would be $23 million per year for 5 years. If the...
A mining company is considering a new project. Because the mine has received a permit, the...
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $9.33 million at Year 0 to mitigate the environmental Problem, but it would not be required to do so. Developing the mine (without mitigation) would cost $54 million, and the expected cash inflows would be $18 million per year for 5 years. If the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT