Question

Your company is considering a project which has the expected cash flows as follows. year 0...

Your company is considering a project which has the expected cash flows as follows.

year 0 1 2 3 4 5 6 7 8 9 10
cash flow -500 90 100 150 180 190 140 100 80 60 -50


The required return for the project is 15% per annum.

(1) What is the NPV?
(2) What are 2 IRRs?
(3) Draw the NPV profile

(4) What are the MIRR?
(5) Should your company take this project?

Homework Answers

Answer #1

1.  PV of cash flows = CFt/ (1+k)^t or CFt x Discount Factor

where CFt is cash flow in year t, k = Cost of capital (WACC) & t is the year of Cash flow

NPV = Sum of PV of all future cash flows - Sum of PV of all Investment

The NPV of the project = 78.93

Year

Cash Flow

Discount Factor @ 15%

Discounted CF

0

-500

1.000

-500.00

1

90

0.870

78.30

2

100

0.756

75.60

3

150

0.658

98.70

4

180

0.572

102.96

5

190

0.497

94.43

6

140

0.432

60.48

7

100

0.376

37.60

8

80

0.327

26.16

9

60

0.284

17.04

10

-50

0.247

-12.35

NPV

78.92

2. The project has 2 IRRs (Since their is an investment in the last year of the project)

Can be found using the excel function for IRR

IRR = 19.45%

IIR 2 = - 59.90%

3. NPV Profile chart - NPV at various levels of discount rate (ranging from 0% to 30%

4. MIRR = (FVCF / PVCF)^(1/n) - 1

Where:

FVCF – the future value of positive cash flows discounted at the reinvestment rate

PVCF – the present value of negative cash flows discounted at the financing rate

n – the number of periods

FVCF = CFt x (1+ Investment Rate)^ (Time left for project)

Year

Cash Flow

Future Value of Positive Cash Flows at 15%

Present Value of Negative Cash Flows @15%

0

-500

-500.00

1

90

316.609

2

100

305.902

3

150

399.003

4

180

416.351

5

190

382.158

6

140

244.861

7

100

152.088

8

80

105.800

9

60

69.000

10

-50

-12.36

PV

2391.77

-512.36

MIRR = (FVCF / PVCF)^(1/n) - 1

MIRR = (2391.77/ 512.36)^ (1/10) -1

= (4.668^(1/10)) -1

= 1.16658 -1

MIRR = 16.66%

5. The company should go ahead with the project as NPV is greater than 0 and MIRR is greater than discount rate

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows Time Project A Project B 0 ($375) ($575) 1 ($300) $190 2 ($200) $190 3 ($100) $190 4 $600 $190 5 $600 $190 6 $926 $190 7 ($200) $0 a. If each project's cost of capital is 12%, which project should be selected? If the cost of capital is 18%, what project is the proper choice? @ 12% cost...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1 2 3 4 5 Cash flows -$1,000 $375 $425 $250 $110 $100 If WACC is 10%, what is NPV, and should the company accept the project? Find IRR, MIRR, payback, and discounted payback period.
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1 2 3 4 5 Cash flows -$1,000 $375 $425 $250 $110 $100 If WACC is 10%, what is NPV and should the company accept the project? Find IRR, MIRR, payback, and discounted payback period. Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 Project A has...
A company is considering a project with the following cash flows: Time Cash Flow 0 -$100...
A company is considering a project with the following cash flows: Time Cash Flow 0 -$100 <<<<<<< negative 1 $100 2 -$100 <<<<<<< negative 3 $120 At a cost of capital of 10%: a. What is the NPV? b. What is the Modified Internal rate of Return? Should the company accept this project?
Here are the net cash flows for a project your company is considering: Year 0 =...
Here are the net cash flows for a project your company is considering: Year 0 = -1000 Year 1 = 250 Year 2 = 449 Year 3 = 800 Year 4 = 500 Year 5 = 500 If the payback period with interest is 3 years, for what range of interest rates is this project worth doing (start your analysis with an interest rate of 0%)?
Polk Products is considering an investment project with the following cash flows (in 000s): Year 0...
Polk Products is considering an investment project with the following cash flows (in 000s): Year 0 Year 1 Year 2 Year 3 Cashflow -100 90 90 30 The company has a 10% cost of capital. What is the payback period for the project? What is the discounted payback period for the project? What is the IRR for the project? What is the NPV for the project? What is the MIRR for the project?                                           PLEASE SHOW STEPS AND SOLUTION
You are considering the following project. Your cost of capital is 8%. The cash flows are...
You are considering the following project. Your cost of capital is 8%. The cash flows are as follow: Year 0 1 2 3 4 -1000 400 100 500 500 What is the NPV of this project? A. 389 B. 221 C. 500 D. 1500
Suppose your firm is considering investing in a project with the cash flows shown below, that...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively. Time 0 1 2 3 4 5 6 Cash Flow -990 190 410 610 610 210 610 Use the NPV decision rule to evaluate this project; should it be accepted or...
Suppose your firm is considering investing in a project with the cash flows shown below, that...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively.      Time: 0 1 2 3 4 5   Cash flow –$310,000 $50,800 $69,000 $111,000 $107,000 $66,200    Use the MIRR decision rule to evaluate this project. (Do not round intermediate calculations....
A company is evaluating a project with the following cash flows: Year CASH FLOW 0 -49,000...
A company is evaluating a project with the following cash flows: Year CASH FLOW 0 -49,000 1 13,700 2 25,200 3 30,500 4 19,800 5 -8,500 The company uses an interest rate of 10% on all projects, Calculate the MIRR of the project using all three methods