Your options for shipping
$99 comma 790
of machine parts from Hamilton to Kuala Lumpur, Malaysia, are (1) use a ship that will take
29
days at a cost of
$3 comma 880
,
or (2) truck the parts to Vancouver and then ship at a total cost of
$4 comma 820
.
The second option will take only
22
days. You are paid via a letter of credit the day the parts arrive. Your holding cost is estimated at
30
%
of the value per year.
a)
▼
Alternative 1
Alternative 2
is more economical, with a daily holding cost of
$nothing
.
(Enter your response rounded to two decimal places.)
b) What issues are not included in the data presented?
A.
For each additional day it takes to deliver the parts, you forgo the interest you could have earned on the payment.
B.
For each additional day it takes to deliver the parts, customer satisfaction is likely to decrease.
C.
For each additional day it takes to deliver the parts, total fuel costs for shipping increase.
Answer : (a.) Calculation for which machine is economical :
First we need to calculate Holding Cost per Day
Holding Cost per Day = 99790 * 30% = 29937 / 365 = 82.019
There will be saving for 7 days(29 - 22)
Holding Cost of 7 days = 82.019 * 7 = 574.13
Cost Saving = 940 (4820 - 3880)
Holding Cost is less than the Cost Saving,Therefore Alternative 1 will be preferrable.
(b.) Correct Option is For each additional day it takes to deliver the parts, customer satisfaction is likely to decrease.Due to delay in delivery customer will not be satisfied.