Question

When two mutually exclusive projects have different lives, how can an analyst determine which is better?...

When two mutually exclusive projects have different lives, how can an analyst determine which is better? What is the underlying assumption in this method?

Homework Answers

Answer #1

I have answered the question below

Please up vote for the same and thanks!!!

Do reach out in the comments for any queries

Answer:

When we have to select from two mutually exclusive projects with different lives, instead of choosing the project with greater NPV or lower NPV of costs, we should select the project with greater Equivalent Annual Revenue(EAR) or lesser Equivalent Annual Cost(EAC).

The basic underlying assumption made here is that we will continue to operate with the same equivalent annual revenue(EAR) or equivalent annual cost(EAC) in the future for the basis of selection criteria amonh the two projects

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
When mutually exclusive projects have different lives, a company should select the project with the ____...
When mutually exclusive projects have different lives, a company should select the project with the ____ Highest IRR Longest life Lowest equivalent annual cost Highest NPV discounted at the cost of capital
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have the same initial outlay. Project Adam has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are not repeatable. What should you do? You should do Project...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
The Meacham Tire Company is considering two mutually exclusive projects with useful lives of 3 and...
The Meacham Tire Company is considering two mutually exclusive projects with useful lives of 3 and 6 years. The after-tax cash flows for projects S and L are listed below. Year Cash Flow S Cash Flow L 0 -$60,000 -$115,000 1 38,000 28,500 2 25,000 49,500 3 35,000 26,850 4 22,600 5 18,750 6 23,500 The required rate of return on these projects is 14-percent. What decision should be made (i.e., which project should be accepted, if indeed any project...
The Meacham Tire Company is considering two mutually exclusive projects with useful lives of 3 and...
The Meacham Tire Company is considering two mutually exclusive projects with useful lives of 3 and 6 years. The after-tax cash flows for projects S and L are listed below. Year Cash Flow S Cash Flow L 0 -$60,000 -$115,000 1 38,000 28,500 2 25,000 49,500 3 35,000 26,850 4 22,600 5 18,750 6 23,500 The required rate of return on these projects is 14-percent. What decision should be made (i.e., which project should be accepted, if indeed any project...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the...
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the firm’s production capacity. The relevant cash flows for the projects are shown in the following table. The firm’s cost of capital is 15%. PROJECT B PROJECT C YEAR Cash Flow Cash Flow 0 350000 50000 1 45000 24000 2 65000 22000 3 65000 19500 4 440000 14600 a) Calculate the period back of each project, assess its acceptability, and indicate which project is best,...
 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​...
 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm's warehouse capacity. The relevant cash flows for the projects are shown in the following​ table: LOADING... . The​ firm's cost of capital is 1212​%. a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b.  Which project is​ preferred? Initial investment 500000 320000 Year 1 130000 130000 2 130000 100000 3 170000...
What are independent and mutually exclusive projects? How can you tell the difference?
What are independent and mutually exclusive projects? How can you tell the difference?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT