Question

Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do...

Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Time 0 1 2 3 4 5

Cash flow -$2800 $870 $870 $780 $560 $360

IRR ___ %

Homework Answers

Answer #1

Internal rate of return is the rate at which if we discount all the future cash flows, the resulting NPV will be zero, it is minimum rate of return that management seeks from the project, IRR of te asset/project must be greater than the required rate of return, otherwise it will not be feasible for the management to accept the project. Best way to calculate IRR is using Excel.

Year

Cash flow

0

-2800

1

870

2

870

3

780

4

560

5

360

IRR

8.42%

Formula

=IRR(J21:J31)

IRR = 8.42%

--------------------------------------------------------------------------------------------------------------------------

Feel free to comment if you need further assistance J

Pls rate this answer if you found it useful.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)         Project E   Time: 0 1 2 3 4 5   Cash flow –$2,700 $830 $840 $760 $540 $340 IRR % ____________ Should the project be accepted or rejected? _________
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Time: 0 1 2 3 4 5 Cash Flow: -$1,800 $670 $720 $680 $460 $260 IRR _____________ % Should the project be accepted or rejected?
Problem 13-9 IRR (LG13-4) Compute the IRR static for Project E. The appropriate cost of capital...
Problem 13-9 IRR (LG13-4) Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,600 $590 $660 $640 $420 $220
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,300 $1,000 $870 $910 $560 $360 Discounted payback period    years
Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent....
Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time 0 1 2 3 4 Cash Flow -11,000.00 5330.00 4180.00 1520.00 2000.00
Compute the IRR statistic for Project F. The appropriate cost of capital is 11 percent. (Do...
Compute the IRR statistic for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: −$11,600 $4,150 $4,980 $2,320 $2,950 Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,200 $390 $520 $560 $640 $140 Problem 13-3 NPV with Non-normal Cash Flows (LG13-3) Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative...
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent....
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,500 $650 $780 $950 $600 $400
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. Having a hard time coming up with the solution to this problem. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: Cash flow: –    0          1          2       3         4      5                      $2,000   $880 $780   $820 $500 $300 Should I accepted or rejected the problem? Discounted...
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal place.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,300 $3,610 $4,440 $1,780 $560 NPV $ _________ Should the project be accepted or rejected? _____________