Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 19 percent.
Year
Project M
Project N
0
-$140,000
-$355,000
1
$63,500
$152,500
2
$81,500
$180,000
3
$72,500
$137,500
4
$58,500
$110,000
What is the IRR for each project?
What is the NPV for each project?
Which,if either, of the projects should the company accept?
Project M
Let the IRR be x.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
140,000 = 63,500 /(1.0x) +81,500/ (1.0x)^2 +72,500 /(1.0x)^3+ $ 58,500 /(1.0x)^4
Or x= 34.471%
Hence the IRR is 34.47%
Project N
Let the IRR be y.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
355,000 =152,500/(1.0y) + 180,000 / (1.0y)^2 + 137,500 /(1.0y)^3 + 110,000/(1.0y)^4
Or y= 24.608%
Hence the IRR is 24.61%
-------------------------------------
NPV of Project = Present Value of Cash Inflow - Present Value of cash Outflow
Project M :
= [ $ 63,500 * 1/ (1.19) ^ 1+ $ 81500* 1/ (1.19) ^ 2 + $ 72500* 1/ (1.19) ^ 3 + $ 58500* 1/ (1.19) ^ 4] - $ 140,000
= $ 43,108.55
Hence the correct answer is $ 43,108.55
Project N :
= [ $ 152,500 * 1/ (1.19) ^ 1+ $ 180000* 1/ (1.19) ^ 2 + $ 137500* 1/ (1.19) ^ 3 + $ 110000* 1/ (1.19) ^ 4] - $ 355,000
= $ 36,709.17
Hence the correct answer is $ 36,709.17
----------------------------------
Since the Net Present Value of Project M is more than the Net Present Value of Project N, the Project M must be accepted.
Hence the correct answer is Project M.
Get Answers For Free
Most questions answered within 1 hours.