Question

You have just used the NPV method to determine that with a cost of capital of...

You have just used the NPV method to determine that with a cost of capital of 10% a particular project is easily rejected. What else do you know for sure?

Group of answer choices

The project will have an IRR greater than 10%

The project will have an IRR less than 10%

Not enough information to answer

The project will have an IRR of exactly 10%

Homework Answers

Answer #1

Answer: Option (2) The project will have an IRR less than 10%

Given that We have just used the NPV method to determine that with a cost of capital of 10%, a particular project will be easily rejected. Which implies that the NPV of the Project @ 10% is negative, Which means the Present Value of Cash Inflows of the Project discounted at 10% is not sufficient to recover the Present Value of Cash Outflows.

Which implies the Return(IRR) generated by this Project is Less than 10%.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The NPV of a project decreases with discount rate r. When r=10%, NPV=$10 million; when r=11%,...
The NPV of a project decreases with discount rate r. When r=10%, NPV=$10 million; when r=11%, NPV= -$5 million. The IRR of this project must be ________. Group of answer choices a. Above 11%. b. Below 10%. c. Not enough information. d. Between 10% and 11%.
Assume capital projects A and B both have a 5-year life. If the NPV profile for...
Assume capital projects A and B both have a 5-year life. If the NPV profile for Project A is much steeper than the NPV profile for Project B, then Project A's future cash inflows tend to come in mostly towards the end of the project, while Project B's cash inflows tend to come in mostly towards the beginning of the project. False No answer text provided. No answer text provided. True If a capital investment project has an NPV >...
You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B...
You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B has an IRR of 8% The crossover rate is 6% Which project will have the greatest NPV if the Required Return is 4% Group of answer choices Project A and B would have the same NPV There is not enough information to answer this question. Project B Project A
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. If a project's NPV is less than zero, then its IRR must be less than the cost of capital. If a project's NPV is greater than zero, then its IRR must...
Tom just got out of a meeting with felicity in which they discussed a capital budgeting...
Tom just got out of a meeting with felicity in which they discussed a capital budgeting project they are evaluating for the company. Tom's mind was not focused on the meeting, so all he can remember is that Felicity used one of the time value of money techniques mentioned in the book to evaluate the project and that she concluded the project should be purchase. based on this information, which of the following statements must be correct? A. The projected...
Which of the following statements is not correct? Group of answer choices The binomial option pricing...
Which of the following statements is not correct? Group of answer choices The binomial option pricing model when taken to the limit becomes the Black-Scholes option pricing model. The Black-Scholes model uses a continuous time discount factor. The binomial option pricing model use a ratio of the range values as the hedge ratio. The Black-Scholes model is related to a heat transfer equation and Brownian molecular motion. The Black Scholes model only estimates the intrinsic value of the call option....
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
To prepare for this Discussion, assume that you have just estimated the cash flows and NPV...
To prepare for this Discussion, assume that you have just estimated the cash flows and NPV for a project your company is considering. Your estimated NPV was +$10. The CFO is not sure whether to accept or reject the project. Post an analysis of the feasibility of the project the CFO is considering based on estimated cash flows and NPV. In your analysis, answer the following: What type of analysis would you use to make a business case for or...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from Project L are $15,000, while the undiscounted cash flows from Project S total $13,000. Their NPV profiles cross at a discount rate of 10 percent. Which of the following statements best describes this situation? Please leave an explanation.  a. The NPV and IRR methods will select the same project if the cost of capital is greater than 10 percent; for example, 18 percent. b. The...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT