Question

You are considering the following two mutually exclusive projects. Both projects will be depreciated using straight-line...

You are considering the following two mutually exclusive projects. Both projects will be depreciated using straight-line depreciation to a zero book value over the life of the project. Neither project has any salvage value.

Project A

Year Cash Flow
0 -$75,000
1 $19,000
2 $48,000
3 $12,000

Project B

Year Cash Flow
0 -$70,000
1 $10,000
2 $16,000
3 $72, 000

Required rate of return 10% 13%
Required payback period 2.0 years 2.0 years

Based on the net present value method of analysis and given the information in the problem, you should:

A. accept both project A and project B.

B. accept project A and reject project B.

C.  accept project B and reject project A.

D. reject both project A and project B.

E. accept whichever one you want as they represent equal opportunities.

Homework Answers

Answer #1

The NPV of the project is computed as shown below:

= Initial investment + Present value of future cash flows

So, the NPV of project A is computed as follows:

= - $ 75,000 + $ 19,000 / 1.10 + $ 48,000 / 1.102 + $ 12,000 / 1.103

= - $ 9,042.07 Approximately

The NPV of project B is computed as follows:

= - $ 70,000 + $ 10,000 / 1.13 + $ 16,000 / 1.132 + $ 72,000 / 1.133

= $ 1,279.52 Approximately

Since the NPV of project A is negative. Hence only Project B shall be accepted.

So, the correct answer is option c.

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering the following two mutually exclusive projects with the following cash flows:                           &nbsp
You are considering the following two mutually exclusive projects with the following cash flows:                                                                                  Project A                                  Project B                                                             Year    Cash Flow                   Year    Cash Flow                                                             0          -$75,000                         0       -$70,000                                                             1          $19,000                         1       $10,000                                                             2          $48,000                         2       $16,000                                                             3          $12,000                         3       $72,000                        Required rate of return                     10 %                                        13 %                             Calculate the NPV, IRR,...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are 2.5 and 3.5 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -1,000 300 400 700   Project B Cash Flow -500 200 400 300 Use the payback decision rule to evaluate these projects;...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?20,000 10,000 30,000 1,000 Project B Cash Flow ?30,000 10,000 20,000 50,000 Use the MIRR decision rule to evaluate...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -30,000 20,000 40,000 11,000   Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 9 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -21,000 11,000 31,000 2,000   Project B Cash Flow -31,000 11,000 21,000 51,000 Use the NPV decision rule to evaluate these...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -29,000 19,000 39,000 10,000   Project B Cash Flow -39,000 19,000 29,000 59,000 Use the PI decision rule to evaluate these...
19. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
19. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -32,000 22,000 42,000 13,000   Project B Cash Flow -42,000 22,000 8,000 62,000 Use the payback decision rule to evaluate...
You are considering the following two mutually exclusive projects. The required rate of return is 12%...
You are considering the following two mutually exclusive projects. The required rate of return is 12% for project A and 11% for project B. Which project should you accept and why? Year Project A Project B 0           -$68,000   -$75,000 1                     28,000 15,000 2                     20,000   20,000 3                     20,000 20,000 4                     10,000 30,000