Calculate the return on investment (ROI) for the following five projects, total cost includes the initial investment. Which projects should be invested in if the organization has a spending constraint of $7,000,000 and its cost of capital is 6%?
Total Total
Project Investment Revenue Cost Profit ROI
A $3,000,000 $5,500,000 $5,000,000 _____ _____
B $2,400,000 $4,000,000 $3,800,000 _____ _____
C $1,350,000 $2,400,000 $2,300,000 _____ _____
D $1,500,000 $3,200,000 $3,000,000 _____ _____
E $2,000,000 $3,800,000 $3,700,000 _____ _____
Profit | ROI | Ranking |
|
Total revenue -cost | Profit /Total investment | ||
A | 5500000-5000000=500000 |
500000/3000000= .1667 or 16.67% |
1 |
B | 4000000-3800000=200000 | 200000/2400000= .0833 or 8.33% | 3 |
C | 2400000-2300000=100000 | 100000/1350000=.0741 or 7.41% | 4 |
D | 3200000-3000000=200000 | 200000/1500000=.1333 or13.33% | 2 |
E | 3800000-3700000=100000 | 100000/2000000=.05 or5% | 5 |
Since Project A has highest ROI then it should be selected first (3,000,000) then project D (1,500,000) and project B (2,400,000) .Total Invetment : 6,900,000
since there is a constraint of 7,000,000 ,project C cannot be undertaken .Project E cannot be accepted as its ROI is less than cost of capital