Question

Rio Tinto is planning a strip-mining project that costs $90,000 initially and generates the following cash...

Rio Tinto is planning a strip-mining project that costs $90,000 initially and generates the following cash flows:

Year 1: $131,000

Year 2: $98,980

Year 3: -$147,650

Cash flow in Year 3 will be spent to restore the terrain, hence it is negative. The required return is 13.5%. Which of the following statements would you most agree with?

A. At a discount rate of 41.092%, the present value of future cash flows is close to $90,000. Hence, the breakeven rate is very high (compared to 13.5%). So, we should accept it.

B. Accept the project since it is a good investment.

C. Reject the project since it does not break even if we ignore discounting.

D. When cash flow signs change more than once, it is tricky to reach a definitive conclusion. It is too risky to accept the project in such situation.

E. Reject the project since the return 10.09%, which is lower than 13.5%.

Homework Answers

Answer #1
YEAR CASH FLOWS DISCOUNT FACTOR OF 13.5% DISCOUNTED CASH FLOWS DISCOUNT FACTOR OF 41.092% DISCOUNTED CASH FLOWS DISCOUNT FACTOR OF 10.09% DISCOUNTED CASH FLOWS
0 -90000 1 -90000 1 -90000 1 -90000
1 131000 0.881057269 115418.5022 0.708757407 92847.22025 0.908347716 118993.5507
2 98980 0.776261911 76834.40393 0.502337061 49721.32233 0.825095572 81667.95974
3 -147650 0.683931199 -100982.4415 0.356035113 -52568.5844 0.749473678 -110659.7886
SUM OF DISCOUNTED CASH FLOW 1270.464611 SUM OF DISCOUNTED CASH FLOW -0.041818518 SUM OF DISCOUNTED CASH FLOW 1.721896582

In the given situation , I will agree with Option A.

Here 41.092% shows internal rate of return where present value of future cash flows equals to cash out flows at year 0.

Hence we should accept the project

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow...
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow year one: $120,000 Cash flow year two: $300,000 Cash flow year three: $193,000 Cash flow year four: $120,000 a. Using a discount rate of 11% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 14%? c. Should the company accept or reject it...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50 and $100, at the end of the first and second years, respectively. (There is no cash flow after the second year) The firm uses a hurdle rate of 15% for projects of similar risk. Determine whether you should accept or reject the project based on NPV. Determine whether you should accept or reject the project based on IRR. Determine whether you should accept or...
Bohrer Mining, Inc., is trying to evaluate a project with the following cash flows: Year Cash...
Bohrer Mining, Inc., is trying to evaluate a project with the following cash flows: Year Cash Flow 0 -$38,100,000 1 62,100,000 2 -11,100,000 a-1 What is the NPV for the project if the company requires a return of 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) a-2 Should the firm accept this project? b. This project has two IRRs, namely ____?____ percent and ____?____ percent, in order from smallest to largest....
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost:...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost: ​$200,000 Cash flow year​ one: ​$23,000 Cash flow year​ two: ​$72,000 Cash flow year​ three: ​$157,000 Cash flow year​ four: ​$157,000 a.  Using a discount rate of 10​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b.  Should the company accept or reject it using a discount rate of 14​%? c.  Should the company accept...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial cost  ...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial cost   Cash flow year one   Cash flow year two   Cash flow year three   Cash flow year four $463,000   $124,000   $240,000   $185,000   $124,000 a. Using a discount rate of 99​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 1717​%? c. Should the company accept...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for 6 years. What is the discounted payback period for this project if the cost of capital is 21%? A) 3.92 years B) 5.61 years C) 4.86 years D) 5.85 years What is the NPV for this project is the cost capital is 21%? A) $157.65 B) -$110.23 C) $199.36 D) $223.08 What is the NPV for this project if the cost of capital is...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require...
Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,500,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama Mining Company’s WACC is...
Consider a project that costs $5000 and has an expected future cash flow of $1000 per...
Consider a project that costs $5000 and has an expected future cash flow of $1000 per year forever. If we wait one year, the cost will increase to $6000 and the expected future cash flow will increase to $1200. If the required return is 10%, should we accept the project? If we should, when should we start the project and why please shows steps please.