Question

1(a). When NPV less than 0, then: Select one: a. IRR=0 b. IRR greater than required...

1(a). When NPV less than 0, then: Select one:

a. IRR=0

b. IRR greater than required return

c. IRR less than 0

d. IRR less than 0

e. IRR less than required return

1(b). When IRR greater than required return, then: Select one:

a. NPV greater than 0

b. NPV less than required return

c. NPV greater than required return

d. NPV=0

e. NPV less than 0

Homework Answers

Answer #1

1(a).

e. IRR less than required return

IRR is the rate at which NPV is zero.Further, NPV and required return has inverse relation.It means if required return is higher then NPV is lower and required return is lower than NPV is higher.At IRR NPV is zero. Negative NPV means higher required return.So it can be said that IRR is lower than required return because at IRR NPV is zero and NPV is less than zero at return higher than IRR.

1b)

a. NPV greater than 0

Consider explanation said above first of all for this question too. At IRR ,NPV is zero.IRR greater than required return ,It means required return is lower than IRR and so at lower discount rate NPV is higher.Hence, NPV is greater than 0. .

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Which of the following statement is incorrect? Select one: a. When the internal rate of return...
Which of the following statement is incorrect? Select one: a. When the internal rate of return is less than this required rate of return, the project is rejected. b. When NPV equals zero, the required rate of return, or discount rate used in the NPV calculation, is greater than the projected rate of return, IRR. c. Most of the answers are correct. d. The number of time periods it takes to cover the initial investment is called the payback period....
If the NPV of a project with one sign reversal in negative, then the project's IRR...
If the NPV of a project with one sign reversal in negative, then the project's IRR ____________ the firm's required rate of return could be greater or less than is exactly equal to must be greater than must be less than
Personal income Select one: A. is always greater than national income. B. is always less than...
Personal income Select one: A. is always greater than national income. B. is always less than national income. C. will always equal national income. D. may be greater than or less than national income.
Which of the following statement is correct? Select one: a. All the answers are incorrect. b....
Which of the following statement is correct? Select one: a. All the answers are incorrect. b. A positive NPV means that the firm’s value will decrease if the project is adopted because the new project’s estimated return is lesst than the firm’s required rate of return. c. Reject the project if the IRR is greater than or equal to the required rate of return. d. Payback period is the discount rate that forces the NPV to equal zero. e. All...
If the NPV of an independent project is higher than zero, this means that: Select one:...
If the NPV of an independent project is higher than zero, this means that: Select one: a. The project should be accepted. b. Not accepting the project decreases the value of the firm. c. The cash flows of the project provide a lower return than the required. d. The project is not acceptable on a risk adjusted basis. e. The firm’s stock price and consequently the wealth of its shareholders will decrease.
Which one of the following indicates a project should be accepted? A. NPV < 0 B....
Which one of the following indicates a project should be accepted? A. NPV < 0 B. IRR>WACC C. IRR<WACC D. NPV=1
Which one of the following statements is TRUE? Group of answer choices When the required return...
Which one of the following statements is TRUE? Group of answer choices When the required return is less than the internal rate of return, net present value is positive. When the IRR is greater than the required return, the net present value is negative. If projects are mutually exclusive, you should always select the project with the greatest IRR. Projects with conventional cash flows have multiple internal rates of return.
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of...
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash flows if WACC is 20%? Time: 0 1 2 3 4 5 -$350,000 $100,000 $100,000 $100,000 $50,000 $50,000 NPV= IRR= Payback period= b) Should you accept or reject the project according to NPV and IRR? *can you please include greater than an less than signs.* Thank you.
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less...
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less than 1; greater than 1 Less than 0; greater than 0 Greater than 1; less than 1 Greater than 0; less than 0 Equal to 1; Greater than 1 Equal to 0; Greater than 0
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT