Question

1(a). (TRUE or FALSE?) We calculate the payback period for a proposed project by adding a...

1(a). (TRUE or FALSE?) We calculate the payback period for a proposed project by adding a project’s positive cash flows, one period at a time, until the sum equals the initial investment.

1(b). (TRUE or FALSE?) When evaluating proposed projects with the IRR method, those projects with IRRs that are greater than the required rate of return are rejected.

1(c). (TRUE or FALSE?) If the project’s IRR is greater than or equal to the hurdle rate (discount rate), the project is rejected.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1(a). (TRUE or FALSE?) Whenever there is a ranking conflict between net present value and internal...
1(a). (TRUE or FALSE?) Whenever there is a ranking conflict between net present value and internal rate of return we generally suggest that the project with the highest net present value be chosen. 1(b). (TRUE or FALSE?) The acceptable independent projects can be ranked by using the IRR methodology, from lowest to the highest IRR. 1(c). (TRUE or FALSE?) When evaluating proposed projects with the IRR method, those projects with IRRs that are less than the required rate of return...
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR...
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR that is greater than the discount rate if the proposed capital budgeting projects are independent. 1(b). (TRUE or FALSE?) Projects with NPVs of positive values will reduce the firm’s value but it just meet the firm’s requirements.
If the payback period equals the projects life, the IRR will be equal to zero True...
If the payback period equals the projects life, the IRR will be equal to zero True or False
You are considering a project with conventional cash flows and the following characteristics: Discounted Payback 2.95...
You are considering a project with conventional cash flows and the following characteristics: Discounted Payback 2.95 Years NPV $510,000 IRR 12% Which of the following statements is correct given this information? I. The discount rate used in computing the net present value was greater than 12%. II. The payback period must be greater than 2.95 years. III. This project should be accepted as the NPV is positive.
The NPV and payback period Suppose you are evaluating a project with the cash inflows shown...
The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $400,000 Year 2 600,000 Year 3 500,000 Year 4 475,000 If the project’s desired rate...
True or False? 1. Payback period fails to account for different levels of risk. ​ 2....
True or False? 1. Payback period fails to account for different levels of risk. ​ 2. Based on the IRR decision rule, you reject a project if the IRR is less than 0. ​ 3. The net present value tells you how much the value of a firm is expected to change by accepting and implementing the project. 4. The training required in order to operate new equipment is included in the capital budgeting calculation.
11. The NPV and payback period What information does the payback period provide? A project’s payback...
11. The NPV and payback period What information does the payback period provide? A project’s payback period (PB) indicates the number of years required for a project to recover its initial investment using its operating cash flows. As the theoretical soundness of the conventional (undiscounted) PB technique was criticized, the model was modified to incorporate the time value of money-adjusted operating cash flows to create the discounted payback method. While both payback models continue to reflect faulty ranking criteria, they...
For independent projects with conventional cash flows, which of the following can we use as a...
For independent projects with conventional cash flows, which of the following can we use as a requirement for the project to be accepted? Multiple Choice PI greater than 1.0 AAR lower than the required rate Payback period that exceeds the requirement Required discount rate greater than the IRR Discounted payback period less than the payback period
7. The NPV and payback period Suppose you are evaluating a project with the cash inflows...
7. The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $350,000 Year 2 600,000 Year 3 600,000 Year 4 450,000 If the project’s desired...
Which of the following is statements related to capital budgeting is not true? A project is...
Which of the following is statements related to capital budgeting is not true? A project is considered acceptable if its NPV is greater zero. A project whose NPV is greater than its IRR is should be accepted. Both the NPV method and the IRR method of evaluating capital investment projects are widely considered to be superior to the payback method. An NPV of zero signifies that the project's cash flows are just sufficient to repay the invested capital and to...