Question

Before whoever decides to answer the following problems, please DO NOT use excel. I have posted...

Before whoever decides to answer the following problems, please DO NOT use excel. I have posted this question already, and the expert answered using excel to solve this problem. I am not good with excel at all so I did not understand what was given. Would rather have the problem worked out showing the formula and work broken down and written out. Thank you in advance.

You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows:

YEAR --- PROJECT A CASH FLOW --- PROJECT B CASH FLOW
0 ------------- -100,000    ---------------   -100,000
1 --------------- 33,000 ---------------               0
2 --------------- 33,000 ---------------               0
3 --------------- 33,000 ---------------               0
4 --------------- 33,000 ---------------               0
5 --------------- 33,000 ---------------    210,000

If the appropriate discount rate on these projects is 12 percent, which would be chosen and why?

1. What is the NPV of project​ A?

____(round to the nearest cent.)

2. What is the NPV of project​ B?

____(round to the nearest cent.)

Homework Answers

Answer #1

1. The NPV of project A is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

So, the NPV will be as follows:

= - $ 100,000 + $ 33,000 / 1.121 + $ 33,000 / 1.122 + $ 33,000 / 1.123 + $ 33,000 / 1.124 + $ 33,000 / 1.125

= $ 18,957.61 Approximately

2. The NPV of project B is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

So, the NPV will be as follows:

= - $ 100,000 + $ 210,000 / 1.125

= $ 19,159.64 Approximately

Since the NPV of project B is greater than the NPV of project A, hence Project B shall be chosen, since it will add more value to the firm by $ 202.03. ( $ 19,159.64 - $ 18,957.61 ).

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000​) 1    30,000            00 2   30,000            00 3   30,000            00 4    30,000            00 5    30,000   210,000 If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? The NPV of Project B is $nothing.​(Round to the nearest​ cent.)
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)
The Sloan Corporation is trying to choose between the following two mutually exclusive design projects:   ...
The Sloan Corporation is trying to choose between the following two mutually exclusive design projects:    Year Cash Flow (I) Cash Flow (II) 0 –$ 71,000 –$ 17,300 1 33,000 9,350 2 33,000 9,350 3 33,000 9,350     a-1 If the required return is 12 percent, what is the profitability index for both projects? (Do not round intermediate calculations. Round your answers to 3 decimal places, e.g., 32.161.)    Profitability Index   Project I      Project II       a-2 If...
Cori's Sausage Corporation is trying to choose between the following two mutually exclusive design projects: Year...
Cori's Sausage Corporation is trying to choose between the following two mutually exclusive design projects: Year Cash Flow (I) Cash Flow (II) 0 – $ 62,000 – $ 18,200 1 33,000 9,800 2 33,000 9,800 3 33,000 9,800 a-1. If the required return is 12 percent, what is the profitability index for each project? (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)    Profitability Index Project I Project II    a-2. If the...
The net present value (NPV) method estimates how much a potential project will contribute to ____...
The net present value (NPV) method estimates how much a potential project will contribute to ____ and it is the best selection criterion. The _____ the NPV, the more value the project adds; and added value means a ____ stock price. CFt is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use cell references to the input data. I will change the input data in your problem to check alternate solutions. You will turn in a complete working Excel spreadsheet with your solution. 1. A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay of $600 and will return $160 per year for the next seven years; Project Beta requires...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use cell references to the input data. I will change the input data in your problem to check alternate solutions. You will turn in a complete working Excel spreadsheet with your solution. 1. A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay of $600 and will return $160 per year for the next seven years; Project Beta requires...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7%. 0 1 2 3 4 Project A -1,130 680...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7%. 0 1 2 3 4 Project A...
If your able to work out the problems instead of using excel since excel isnt accessible...
If your able to work out the problems instead of using excel since excel isnt accessible on the exam. Consider the following projects, for a firm using a discount rate of 10%. If the projects are mutually exclusive, which, if any, project(s) should the firm accept? Project                   NPV                                           IRR                                            PI E                               $200,000                                10.2%                                       1.04 F                               $(200,001)                            11%                                           .81 G                               $1                                                10%                                           1.01 H                              $(235,000)                            9%                                            .95 a.               E b.              F c.               H d.              F and H You are considering two...