Question

Initial Outlay of a new branch=$3M and is expected to generate $500K in Cash Flow for...

Initial Outlay of a new branch=$3M and is expected to generate $500K in Cash Flow for 10yrs. Multiple choice question

a. If branch is sold for 2M in yr 10, E(r) of new branch=15.02%

b. If branch is sold for 2M in yr 10, E(r) of new branch=11.02%

c. If branch is sold for 2M in yr 10, E(r) of new branch=14.02%

d. If branch is sold for 2M in yr 10, E(r) of new branch=16.02%

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project A would require an initial outlay of $60,000 and is expected to generate positive cash...
Project A would require an initial outlay of $60,000 and is expected to generate positive cash flows in years one through six of $18,838; $12,133; $17,123; $13,007; $17,559; and $17,907. Using a discount rate of 13.2%, what is the NPV of this project? If the answer is negative, include the negative sign, and show the answer to the nearest dollar.
Project A would require an initial outlay of $56,000 and is expected to generate positive cash...
Project A would require an initial outlay of $56,000 and is expected to generate positive cash flows in years one through six of $16,542; $14,677; $15,035; $19,167; $19,796; and $12,120. Using a discount rate of 17.1%, what is the NPV of this project? If the answer is negative, include the negative sign, and show the answer to the nearest dollar.
Consider the following project: Initial outlay = $20 million Year 1 expected cash flow = $7...
Consider the following project: Initial outlay = $20 million Year 1 expected cash flow = $7 million Year 2 expected cash flow = $6 million Year 3 expected cash flow = $5 million Year 4 expected cash flow = $5 million If the cash flows are received uniformly throughout the year, the payback period is closest to:
A project with an initial cost of $27,600 is expected to generate cash flows of $6,700,...
A project with an initial cost of $27,600 is expected to generate cash flows of $6,700, $8,800, $9,150, $8,050, and $7,500 over each of the next five years, respectively. What is the project's payback period? Multiple Choice 3.48 years 3.37 years 3.68 years 3.58 years 3.74 years
A project with an initial cost of $26,550 is expected to generate cash flows of $6,400,...
A project with an initial cost of $26,550 is expected to generate cash flows of $6,400, $8,500, $9,000, $7,900, and $7,200 over each of the next five years, respectively. What is the project's payback period? Multiple Choice 3.71 years 3.71 years 3.54 years 3.45 years 3.34 years
You are considering a project with an initial cash outlay of $100,000 and expected free cash...
You are considering a project with an initial cash outlay of $100,000 and expected free cash flows of $23,000 at the end of each year for 6 years. The required rate of return for this project is 10 percent. a. What is the project’s payback period? b. What is the project’s discounted payback period? c. What is the project’s NPV ? d. What is the project’s PI ? e. What is the project’s IRR ? f. What is the project’s...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $32,500, and its expected cash flows would be $13,050 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
A project needs an initial outlay of $3000 for equipment and will net a cash flow...
A project needs an initial outlay of $3000 for equipment and will net a cash flow of $450 for the next 10 years. At the end of the 10th year, there is a Salvage Value of $1000 for the equipment. What is the NPV of the project if the cost of capital is 12% p.a. effective (to the nearest dollar)? Select one: a. -$953 b. $2500 c. -$135 d. $1585
A company invests in a new project that requires an initial capital outlay of $835087. The...
A company invests in a new project that requires an initial capital outlay of $835087. The project will generate annual net cash flows of $196478 over a period of 9 years. The after-tax cost of capital is 10%. In addition, a working capital outlay of $55156 will be required. This working capital outlay will be recovered at the end of the project’s life. What is the net present value of the project? Select one: a. $264670 b. $296434 c. $933215...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $12,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's...