Question

 Using a cost of capital of 11​%, calculate the net present value for the project shown...

 Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable,

Initial investment

​(CF 0CF0​)

negative $−$1153

Year

​(t​)

Cash inflows

​(CF Subscript tCFt​)

in thousands

1

​$83

2

​$135

3

​$195

4

​$260

5

​$315

6

​$385

7

​$280

8

​$95

9

​$40

10

​$29

The net present value​ (NPV) of the project is

Homework Answers

Answer #1

SOLUTION:-

Calculation of the NPV of the project is as follows:-

  

Years Inflow / Outflow PV of $1 Factor for 11% Discounted Cash outflows Discounted Cash inflows
0 ($1153) 1 ($1153)
1 $83 0.9009 $74.77
2 $135 0.8116 $109.56
3 $195 0.7312 $142.58
4 $260 0.6587 $171.26
5 $315 0.5935 $186.95
6 $385 0.5346 $205.82
7 $280 0.4817 $134.88
8 $95 0.4339 $41.22
9 $40 0.3909 $15.64
10 $29 0.3522 $10.21
Total ($1153) $1092.89

NPV = Discounted future expected net cash inflows - Initial investment

Here,

Discounted future expected net cash inflows = $1092.89

Initial investment = $1153

By substituting the values we get,

NPV = $1092.89 - $1153

  NPV = - $60.11 ( negative NPV)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Using a cost of capital of 11​%, calculate the net present value for the project shown...
Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, Initial investment ​(CF 0CF0​) negative $ 1149−$1149 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) in thousands 1 ​$8080 2 ​$130130 3 ​$189189 4 ​$256256 5 ​$312312 6 ​$376376 7 ​$280280 8 ​$102102 9 ​$4242 10 ​$2020
For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​...
For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. Initial investment ​(CF 0CF0​) ​$80,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 ​$25,000 2 ​$45,000 3 ​$30,000 4 ​$30,000 5 ​$15,000
Internal rate of return For the project shown in the following​ table, calculate the internal rate...
Internal rate of return For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. The​ project's IRR is ​%. (Round to two decimal​ places.) Initial investment ​(CF 0CF0​) $110,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 $25,000 2 $50,000 3 $30,000 4 $35,000 5 $10,000
Internal rate of return For the project shown in the following table, LOADING... , calculate the...
Internal rate of return For the project shown in the following table, LOADING... , calculate the internal rate of return (IRR). Then indicate, for the project, the maximum cost of capital that the firm could have and still find the IRR acceptable. The project's IRR is nothing %. (Round to two decimal places.) Initial investment ​(CF 0CF0​) ​$120 comma 000120,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 ​$20 comma 00020,000 2 ​$35 comma 00035,000 3 ​$45 comma 00045,000 4...
1.A project has an expected net present value of $40,000 with a standard deviation of the...
1.A project has an expected net present value of $40,000 with a standard deviation of the net present value of $30,000. Assume that NPV is normally distributed. (a) What is the probability that the project will have a negative NPV? (b) If the level of tolerance for the project having a negative NPV is 5%, would this project be considered acceptable? Explain why or why not?
When using the Net Present Value method, A project is acceptable if the present value of...
When using the Net Present Value method, A project is acceptable if the present value of benefits equals the present value of outflows. A project is acceptable if the present value of benefits exceeds a specified minimum value. None of the answers provided is correct A project is acceptable if the required rate of return on the project is equal to the cost of the firm’s capital. Projects with positive net present values increase the value of the firm.
Calculate the net present value (NPV) for a 15-year project with an initial investment of $25,000...
Calculate the net present value (NPV) for a 15-year project with an initial investment of $25,000 and a cash inflow of $6,000 per year. Assume that the firm has an opportunity cost of 15%. 1. The project’s net present value is $___. (Round to the nearest cent) 2. Is the project acceptable? Yes or No
If a project has a net present value equal to zero, then: Group of answer choices...
If a project has a net present value equal to zero, then: Group of answer choices the project earns a return exactly equal to the discount rate. the total of the cash inflows must equal the initial cost of the project. a decrease in the project's initial cost will cause the project to have a negative NPV. any delay in receiving the projected cash inflows will cause the project to have a positive NPV. the project's PI must be also...
11. The discount rate that makes the net present value of an investment exactly equal to...
11. The discount rate that makes the net present value of an investment exactly equal to zero is the: A) Payback period. B) Internal rate of return. C) Average accounting return. D) Profitability index. E) Discounted payback period. 12. The internal rate of return (IRR) rule can be best stated as: A) An investment is acceptable if its IRR is exactly equal to its net present value (NPV). B) An investment is acceptable if its IRR is exactly equal to...
The net present value (NPV) method estimates how much a potential project will contribute to ____...
The net present value (NPV) method estimates how much a potential project will contribute to ____ and it is the best selection criterion. The _____ the NPV, the more value the project adds; and added value means a ____ stock price. CFt is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can...