Calculate the total value of the following FTR portfolio on a two node network. We'll label the nodes as Node A and Node B. The LMP at Node A is $20/MWh and the LMP at Node B is $30/MWh. 15 MW FTR from Node A to Node B 10 MW FTR from Node B to Node A
Given data,
given network is two node network;
given nodes are node A ,node B
LMP at node A = $20/Mwh
LMP at node B = $30/Mwh
FTR from node A to node B = 5Mw
FTR from node B to node A = 10Mw
FTR as obligations only are equalent to ARR(Auction Revenue Right)
ARR Target allocation= (ARR MW)*(LMP ARR sink-LMP ARR source).............(1)
From node A to Node B:
submitting values into eq(1)
ARR= (15Mw)*($30-$20)
=(15Mw)*($10)
=($150)
From Node B to Node A:
subdtuting values in eq (1)
ARR=(10MW)*($20-$30)
=(10MW)*(-$10)
=(-$100)
total value of the FTR portfolio= total ARR from Node A to Node B+ total ARR from Node B to Node A
=($150)+(-$100)
=$50