Question

Two sites are currently under consideration for a bridge to cross the Nile River at Elmansoura...

Two sites are currently under consideration for a bridge to cross the Nile River at Elmansoura city, Dakahlia. The first alternative, Suspension bridge, would have a first cost of L.E 30 million with annual maintenance costs of L.E. 15,000. In addition, the concrete deck would have to be resurfaced every 10 years at a cost of L.E. 50,000. The second alternative, Truss Bridge and approach roads, are expected to cost L.E 12 million and have annual maintenance costs of L.E. 8,000. The bridge would have to be painted every 3 years at a cost of L.E. 10,000. In addition, the bridge would have to be sandblasted every 10 years at a cost of L.E. 45,000. The Cost of purchasing right-way is expected to be L.E 800,000 for the suspension bridge and L.E. 10.3 million for the truss bridge. Compare the alternatives on the basis of their capitalized cost if the interest rate is 6 % per year.

Homework Answers

Answer #1

Capitalized cost of suspension bridge = 30000000 + 15000 / 0.06 + 50000*(A/F,6%,10) / 0.06 + 800000

= 30000000 + 15000 / 0.06 + 50000*0.075868 / 0.06 + 800000

= 31113223.33 ~ 31,113,223

Capitalized cost of truss bridge = 12000000 + 8000 / 0.06 + 10000*(A/F,6%,3) / 0.06 + 45000*(A/F,6%,10) / 0.06 + 10300000

= 12000000 + 8000 / 0.06 + 10000*0.314110 / 0.06 + 45000*0.075868 / 0.06 + 10300000

= 22,542,586

As capitalized cost of truss bridge is less, it should be selected

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.04 million, and the concrete option has an initial cost of $2.5 million. Every 25 years, the steel bridge must be painted at a cost of $450,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
1. A new bridge with a 100-year life is expected to have an initial cost of...
1. A new bridge with a 100-year life is expected to have an initial cost of Birr 20 million. This bridge must be resurfaced every five years, at a cost of Birr 1 million. The annual inspection and operating costs are estimated to be Birr 50 000. Determine the present-worth cost of the bridge using the capitalized equivalent approach (i.e., take the life of the bridge as infinite). The interest rate is 10% per year, compounded annually.
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.04 million, and the concrete option has an initial cost of $2.52 million. Every 25 years, the steel bridge must be painted at a cost of $790,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.04 million, and the concrete option has an initial cost of $2.5 million. Every 25 years, the steel bridge must be painted at a cost of $450,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
A new bridge across the Cumberland River is being planned. The construction (first) cost of the...
A new bridge across the Cumberland River is being planned. The construction (first) cost of the bridge is $1,900,000 and annual upkeep is estimated to be $25,000. In addition, major maintenance work is anticipated every eight years at a cost of $350,000 per occurrence. The town government’s MARR is 8% per year. 1. For this problem, what analysis period (N) is, practically speaking, defined as forever? 2. If the bridge has an expected life of 50 years, what is the...
A toll bridge across the Ohio River is being considered as a replacement for the current...
A toll bridge across the Ohio River is being considered as a replacement for the current John F. Kennedy I-65 bridge linking Indiana to Kentucky at Louisville. Because this bridge, if approved, would become a part of the United States interstate highway system, benefit-cost analysis must be applied in the evaluation. Initial investment costs of the structure are estimated to be $18,000,000, and $475,000 per year in operating and maintenance costs are anticipated over its 30-year projected lifetime. In addition,...
0-7. A toll bridge across the Mississippi River is being considered as a replacement for the...
0-7. A toll bridge across the Mississippi River is being considered as a replacement for the current I-40 bridge linking Tennessee to Arkansas. Because this bridge, if approved, will become a part of the U.S. Interstate Highway system, the B–C ratio method must be applied in the evaluation. Investment costs of the structure are estimated to be $17,500,000, and $325,000 per year in operating and maintenance costs are anticipated. In addition, the bridge must be resurfaced every fifth year of...
You have four choices. A) To build a “stainless-steel” bridge that will cost you $5 million...
You have four choices. A) To build a “stainless-steel” bridge that will cost you $5 million and last 120 years; or, B) build a regular steel bridge that needs to be replaced after 60 years and today would cost you $4 million and then (in 2020-$) another $4 million in 60 years, or C) build a wooden bridge that costs $3 million and need to be replaced every 20 years (i.e., replaced 5 times to last 120 years) (every time...
A computer platform requires $150,000 initial investment and additional $100,000 after 10 years. The annual software...
A computer platform requires $150,000 initial investment and additional $100,000 after 10 years. The annual software maintenance costs are $6,000 for the first 4 years and $13,000 thereafter. In addition, there is expected to be a recurring major upgrade cost of 19,000 every 13 years. Assuming 5% interest rate, calculate the capitalized value of the project's costs
Two large-scale conduits are under consideration by a large municipal utility district (MUD). The first involves...
Two large-scale conduits are under consideration by a large municipal utility district (MUD). The first involves construction of a steel pipeline at a cost of $225 million. Portions of the pipeline will have to be replaced every 40 years at a cost of $50 million. The pumping and other operating costs are expected to be $10 million per year. Alternatively, a gravity flow canal can be constructed at a cost of $350 million. The M&O costs for the canal are...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT