There are 2 projects. Today, first one pay benefits of 1000€ and
nothing else. Second one today, pays nothing but 1 year later(from
now) 1090€.
1) If discount rate were 0%, which one would be prefered?
2) What about if rate were increased to 10%?
Question
(1)
Project 1 pays 1,000 euros today.
So, the present worth of payment from Project 1 is 1,000 euros.
Project 2 pays 1,090 euros 1 year later.
The discount rate is 0%.
So, the present worth of payment from Project 2 is 1,090 euros.
The present worth of payment from Project 2 is greater.
So,
If discount rate were 0%, we would prefer Project 2.
(2)
Project 1 pays 1,000 euros today.
So, the present worth of payment from Project 1 is 1,000 euros.
Project 2 pays 1,090 euros 1 year later.
The discount rate is 10%.
Calculate the present worth of the payment from project 2
PW = 1,090/(1+0.10)1
PW = 990.91
The present worth of payment from project 2 is 990.91 euros.
The present worth of payment from Project 1 is greater.
So,
If discount rate is 10%, we would prefer Project 1.