Question

Robotek Ltd. Sti. The Humanoid Robot Production Project, whose net cash flows and possibilities are given...

Robotek Ltd. Sti. The Humanoid Robot Production Project, whose net cash flows and possibilities are given below; Calculate the expected value, standard deviation and coefficient of variation in terms of risk and calculate the probability of the project's NPV to be greater than 150 million TL.

                 Humanoid Robot Production Project  

            (000.000,00)                         (%)                                                                              

Net Cash Flow (Ai)                        Possibility (Pi)

   180                                         25

   240                                         65

   300                                         10

Equations You May Need:

NPV = ∑n Rt / (1+k)t - C

               t=1

      ∑m Ct / (1+r)t = ∑n Rt / (1+r)t

t=1                       t=1

profitability index = {∑n Rt / (1+k)t + H / (1+k)n} / {C0=∑n Ct / (1+k)t}

                                  t=1                                                 t=1

E (A) = ∑k Ai * Pi

               i=1

S = √ ∑k [Ai – E (A)]2 * Pi

            i=1

DK = S / E (A)

Z = X – E (NPV) / S

Homework Answers

Answer #1

Expected value = E(A) = =

= 180*0.25 + 240*0.65 + 300*0.10 = 45 + 156 + 30 = 231

= 231 million

Standard deviation = s =

s2 = 0.25(180 - 231)2 + 0.65(240 - 231)2 + 0.1(300 - 231)2 = 0.25*512 + 0.65*92 + 0.1*692 = 0.25*2601 + 0.65*81 + 0.1*4761 = 1179

s = 11790.5 = 34.33657 million

Hence approximately

s = 34.34 million

Coefficient of variation = s/= 34.34/231 = 0.148658 = approximately 14.87%

Coefficient of variation = DK = 14.87%

Note: For calculating NPV, we first need the rate of interest r, which is not given in the question. Please provide it for further answers about NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
2. A project has the following cash flows             C0                    C1    &n
2. A project has the following cash flows             C0                    C1                    C2                    C3                                       ($1000)             $300                $400                $600 What is the project’s payback period? Year 0 1 2 3 Cash Flow ($1000) $300 $400 $600 Cumulative ($1000) ($700) ($300) 300 a. Calculate the projects NPV at 10%. b. Calculate the project’s PI at 10%. c. Calculate an IRR for the project in question 2 How would you answer a,b, and c in excel? I am getting...
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
2. A company is considering a project that has the following cash flows: C0 = -3,000,...
2. A company is considering a project that has the following cash flows: C0 = -3,000, C1 = +900, C2 = +500, C3 = +1,100, and C4 = +1,900, with a risk-adjusted discount rate of 8%. A) Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Modified Internal Rate of Return (MIRR), and Profitability Index (PI) of this project. B) If you were the manager of the firm, will you accept or reject the project based on the...
The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000...
The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000 The NPV of the project at a discount rate of 50% is: A.) 18,000 B.) 5,000 C.) 11,000 D.) zero or E.) none of these The IRR for this project is: A.) 10% B.) 25% C.) 50% D.) 100% or E.) none of these The payback period for this project is: A.) zero years B.) one year C.) two years D.) three years or...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company’s weighted average cost of capital (WACC) is 10%. What are the project’s payback period (Payback), internal rate of return (IRR), net present value (NPV), and profitability index (PI)? A. Payback = 3.5, IRR = 10.22%, NPV = $1260, PI=1.26 B. Payback = 2.6, IRR = 21.22%, NPV = $349, PI=1.35 C. Payback =...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
Pediatrics Partners is evaluating a project with the following net cash flows and probabilitites.... The Year...
Pediatrics Partners is evaluating a project with the following net cash flows and probabilitites.... The Year 5 value includes salvage value. Pediatrics Partners corporate capital of use is 12%. What is the projects expected NPV assuming average risk? What art the projects most likely, worse case, and best case NPV? What is the projects expected NPV on the basis of the scenario analysis? What i the projects standard deviation of NPV? Assume the managers judge the project to have higher...
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows Time Project A Project B 0 ($375) ($575) 1 ($300) $190 2 ($200) $190 3 ($100) $190 4 $600 $190 5 $600 $190 6 $926 $190 7 ($200) $0 a. If each project's cost of capital is 12%, which project should be selected? If the cost of capital is 18%, what project is the proper choice? @ 12% cost...
A project has the following annual net cash flows: Year 0: -19,000 Year 1: 8,000 Year...
A project has the following annual net cash flows: Year 0: -19,000 Year 1: 8,000 Year 2: 11,000 Year 3: 6,000 Year 4: 4,500 1.The firm's WACC is 14%. Calculate IRR. 2. Calculate MIRR for the project in the previous problem. 3. Calculate the project's NPV. (Round to the nearest cent) 4. Calculate the project's EAA. 5. Calculate the project's payback period. 6. Calculate the project's discounted payback period. (Round to two decimal places)
The net present value (NPV) method estimates how much a potential project will contribute to ____...
The net present value (NPV) method estimates how much a potential project will contribute to ____ and it is the best selection criterion. The _____ the NPV, the more value the project adds; and added value means a ____ stock price. CFt is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can...