Question

B- Based on the PW value you got in the previous question, is this investment economically...

B- Based on the PW value you got in the previous question, is this investment economically justified or not? type you explanation below

Homework Answers

Answer #1

Just now I have solved the question with the following information.

Price = $ 134,595, SV = $ 9973, MARR = 15%,

Annual saving = $ 0.1 × 300,000 = $ 30,000

Useful life = 6 years.

Calculating the present worth

As we can see from the calculation that the present worth is negative thus the firm will have to bear loss if it invests in the project. Thus, the project is not economically justified.

Note: Decision rule for PW

If PW > 0, Accept

PW = 0, Indifferent

PW < 0, Reject.

Please contact if having any query will be obliged to you for your generous support. Your help mean a lot to me please help. Thank you.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1)For the below ME alternatives , which machine should be selected based on the PW analysis....
1)For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 25,529 30000 10000 Annual cost, $/year   8,565                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A= 2)For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First...
QUESTION 3 For the below ME alternatives , which machine should be selected based on the...
QUESTION 3 For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 16,122 30000 10000 Annual cost, $/year   8,601                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A= QUESTION 4 For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine...
QUESTION 1 A new production system for a factory is to be purchased and installed for...
QUESTION 1 A new production system for a factory is to be purchased and installed for $132,564. This system will save approximately 300,000 kWh of electric power each year for a 6-year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system will be $9,792 at year 6. Using the PW method to analyzes if this investment is economically justified A- calculate the PW of the...
Question 1 A new production system for a factory is to be purchased and installed for...
Question 1 A new production system for a factory is to be purchased and installed for $142,299. This system will save approximately 300,000 kWh of electric power each year for a 6-year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system will be $9,077 at year 6. Using the PW method to analyzes if this investment is economically justified A- calculate the PW of the...
for the below two machines and based on AW analysis which machine we should select? MARR=10%....
for the below two machines and based on AW analysis which machine we should select? MARR=10%. Machine A Machine B First cost, $ 28,321           100,000 Annual cost, $/year   11,988                7,000 Salvage value, $   5,755 - Life, years 3 infinite Answer the below question: A- the AW for machine A= For the below two machines and based on AW analysis which machine we should select? MARR=10% Machine A Machine B First cost, $ 25,866 115,900 Annual cost, $/year   13,724 8,637 Salvage...
for th below two machines and based on AW analysis which machine we should select? MARR=10%....
for th below two machines and based on AW analysis which machine we should select? MARR=10%. Machine A Machine B First cost, $ 28,321           100,000 Annual cost, $/year   11,988                7,000 Salvage value, $   5,755 - Life, years 3 infinite Answer the below question: A- the AW for machine A= Machine A Machine B First cost, $ 26,419 148,773 Annual cost, $/year   10,229 7,141 Salvage value, $   4,000 - Life, years 3 infinite Answer the below question: B- the AW for...
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 14,991 Annual cost, $/year 8,930 6,000 4,000 Salvage value, $ 4,000   5,000 1,000 Life, years ( A= 3, B= 6. C= 2) Answer the below questions : C- PW for machine C =?
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR is 10%. Machine A Machine B Machine C First cost, $ 15000 30000 13,435 Annual cost, $/year   16,207                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- PW for machine C =
QUESTION 3 For the below ME alternatives , which machine should be selected based on the...
QUESTION 3 For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 16,122 30000 10000 Annual cost, $/year   8,601                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A= QUESTION 4 For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine...
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 21,302 30000 10000 Annual cost, $/year   9,993                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- AW for machine A= For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10% Machine A Machine B Machine C First...