A flood control project with a life of 13 years will require an investment of $55000 and annual maintenance costs of $5500. The project will provide no benefits for the first three years but will save $28000 per year in flood damage starting in the fourth year. The appropriate MARR is 12% per year. What is the modified B-C ratio for the flood control project?
a. 1.25
b.5.72
c. 1.41
d. 2.05
e. 1.86
Initial Cost=I=$55000
Annual maintenance cost=C=$5500
Useful life=n=13 years
MARR=i=12%
Annual benefit =R=$28000 starting in 4th year
PW of maintenance costs=PW(M)=C*(P/A,12%,13)
PW of maintenance costs=PW(M)=5500*6.423548
=$35,329.51
Let us now calculate the PW of benefits which is given by
PWB=R*(P/F,12%,3)*(P/A,12%,10)
(P/F,0.12,3)=1/(1+0.12)^3=0.711780
PWB=28000*0.711780*5.650223 =$112608.04
Modified B-C ratio=(PWB-PWC)/I=(112608.04-35329.51)/55000=1.405
Correct option is
c) 1.41