Question

There are four estimates made for the anticipated cycle time to produce a subcomponent. The estimates,...

There are four estimates made for the anticipated cycle time to produce a subcomponent. The estimates, in seconds, are 10, 20, 30, and 64. If the first two estimates have equal weights, which total 70%, and the last two are weighted equally with the remaining 30%, what is the expected time?

The expected time is  seconds.

Homework Answers

Answer #1

The expected time = (10 * 0.35) + (20 * 0.35) + (30 * 0.15) + (64 * 0.15)

                              = 3.5 + 7 + 4.5 + 9.6

                              = 24.6

Thus, the expected time is 24.6 seconds.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Beech’s managers have made the following additional assumptions and estimates: 1. Estimated sales for July, August,...
Beech’s managers have made the following additional assumptions and estimates: 1. Estimated sales for July, August, September, and October will be $210,000, $230,000, $220,000, and $240,000, respectively. 2. All sales are on credit and all credit sales are collected. Each month’s credit sales are collected 45% in the month of sale and 55% in the month following the sale. All of the accounts receivable at June 30 will be collected in July. 3. Each month’s ending inventory must equal 20%...
Beech’s managers have made the following additional assumptions and estimates: 1. Estimated sales for July, August,...
Beech’s managers have made the following additional assumptions and estimates: 1. Estimated sales for July, August, September, and October will be $280,000, $300,000, $290,000, and $310,000, respectively. 2. All sales are on credit and all credit sales are collected. Each month’s credit sales are collected 35% in the month of sale and 65% in the month following the sale. All of the accounts receivable at June 30 will be collected in July. 3. Each month’s ending inventory must equal 25%...
The cycle time for the robotic assembly of a centrifugal pump is estimated at 22 seconds....
The cycle time for the robotic assembly of a centrifugal pump is estimated at 22 seconds. The current assembly time using manual methods is 30 seconds. Given that the annual production requirement is 460,000 units, discuss the financial viability of using robots for this application. The following additional information is available : Cost of Assembly Robot $75,000 Cost of Safety System $10,000 Cost of Feeders, Tooling etc $30,000 Annual Operating Costs $10,000 Labour Costs (including overheads) $45,000 / worker /...
The company PR Products Corp. estimates that its quarterly sales for the next year are as...
The company PR Products Corp. estimates that its quarterly sales for the next year are as follows: (units) The price per unit is $ 70 1. 1 Quarter 30,000 units 2. 2 Quarter 50,000 3. 3 Quarter 60,000 4. 4 Quarter 40,000 Accounts receivable as of December 31 are $ 90,000. The company estimates that sales are charged 60% in the quarter they are made and 40% in the following quarter. Finished Goods' desired ending inventory represents 20% of next...
Choose one of the following games from the Games Fair: Four Coin Flip Each flip of...
Choose one of the following games from the Games Fair: Four Coin Flip Each flip of the four coins costs 10 points You win: 10 points if you flip two heads 30 points if you flip no heads Five Card Shuffler Each hand of five cards costs 10 points You win: 20 points for no hearts 0 points for one heart 10 points for two hearts 20 points for three hearts 50 points for four hearts 1000 points for five...
Karen is now age 70 (at time 0). For the following questions, you should use the...
Karen is now age 70 (at time 0). For the following questions, you should use the following Life Table and 5% p.a. interest. You may assume that all deaths are independent events. Age x lx 70 150 71 140 72 125 73 105 74 80 75 50 76 40 77 30 78 20 79 10 80 0 If she lives until age 73, she will be entitled to receive a lifetime pension of $25,000 per annum. The first payment will...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
An insurance portfolio consists of two homogeneous groups of clients; N i, (i = 1 ,...
An insurance portfolio consists of two homogeneous groups of clients; N i, (i = 1 , 2) denotes the number of claims occurred in the ith group in a fixed time period. Assume that the r.v.'s N 1, N 2 are independent and have Poisson distributions, with expected values 200 and 300, respectively. The amount of an individual claim in the first group is a r.v. equal to either 10 or 20 with respective probabilities 0.3 and 0.7, while the...
Pinky and The Brain are great friends. They like to play games with numbers. This time,...
Pinky and The Brain are great friends. They like to play games with numbers. This time, Pinky has given The Brain a list of numbers and given him the task of determining if it is possible to choose a subset of them such that they sum is equal to another given number. Build an algorithm using dynamic programming to help The Brain with his problem. INPUT The first line corresponds to N, the amount of numbers given by Pinky The...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT