Question

In the table below you will find a schedule of a firm’s fixed cost and variable...

In the table below you will find a schedule of a firm’s fixed cost and variable cost. Complete the table by computing total cost, average fixed cost, average variable cost, average total cost, and marginal cost.

                

Total

Total

Average

Average

Average

Total

fixed

variable

   Total     

fixed

variable

total

Marginal

product

cost

cost

cost

cost

cost

cost

    cost    

0

80

0

1

80

100

2

80

180

3

80

240

4

80

320

5

80

440

6

80

600

7

80

800

8

80

1040

9

80

1340

10

80

1800

Homework Answers

Answer #1
Total Product Total Fixed Cost Total Variable Cost Total cost Average Fixed Cost Average Variable Cost Average Total Cost Marginal Cost
0 80 0 80 - - - -
1 80 100 180 80 100 180 100
2 80 180 260 40 90 130 80
3 80 240 320 26.67 80 106.67 60
4 80 320 400 20 80 100 80
5 80 440 520 16 88 104 120
6 80 600 680 13.33 100 113.33 160
7 80 800 880 11.43 114.29 125.71 200
8 80 1040 1120 10 130 140 240
9 80 1340 1420 8.89 148.89 157.78 300
10 80 1800 1880 8 180 188 460
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Table given providing you the total product, fixed cost and variable cost, you are required to...
Table given providing you the total product, fixed cost and variable cost, you are required to fill the remaining columns: (marks 20) Total Product Fixed Cost Variable Cost Total cost Average Total Cost Average Fixed Cost Average variable Cost Marginal Cost 0 100 0 1 100 90 2 100 170 3 100 240 4 100 300 5 100 360 6 100 450 7 100 540 8 100 650 9 100 780 10 100 930 Table given providing you the total...
Fill in the blanks in the following table: output total cost total fixed cost total variable...
Fill in the blanks in the following table: output total cost total fixed cost total variable cost average fixed cost average variable cost average total cost marginal cost 100 4500 3500 1000 35 10 45 200 9 8 300 9.50 400 7300 8.75 500 4890 16.78 600 6000 10 700 5 12.50 800 12150 15.19 A) complete the table B) do your numbers in the table illustrate the expected relation between average variable cost and marginal cost? between average total...
The table below refers to the production cost of Syarikat Sonata Enterprise. Quantity Fixed Cost Variable...
The table below refers to the production cost of Syarikat Sonata Enterprise. Quantity Fixed Cost Variable Cost Total Cost Average Total Cost Marginal Cost 0 100 0 - - 1 20 2 35 3 50 50 4 100 150 37.5 0 5 -10 6 100 -12 Based on the table, answer the following questions. a)  Complete the table above. (1/2 mark for each correct answer = Total 10 marks) b)  Calculate the Average Variable Cost (AVC) and Average Fixed Cost (AFC) at...
The table shows the cost schedule for Eclipse Enterprise. Output (Unit) Total Fixed Cost (RM) Total...
The table shows the cost schedule for Eclipse Enterprise. Output (Unit) Total Fixed Cost (RM) Total Variable Cost (RM) Total Cost (RM) Average Fixed Cost (RM) Average Variable Cost (RM) Average Cost (RM) Marginal Cost (RM) 0 20 1 50 2 70 3 86 4 110 5 150 6 206 7 270 Question: Complete the following cost schedule for Eclipse Enterprise.       My answer table below: (if my answer table wrong, pls correct it. If possible show calculate getting answer....
complete the table below: Output Total Cost Variable Cost FIxed Cost Marginal Cost 0 50 1...
complete the table below: Output Total Cost Variable Cost FIxed Cost Marginal Cost 0 50 1 60 2 75 3 100 4 150 5 225 6 400
Use the total cost(TC) schedule that is presented in the the table below to calculate average...
Use the total cost(TC) schedule that is presented in the the table below to calculate average total cost, average variable cost, average fixed cost and marginal cost when output (Q) is equal to 6 Q TC 0 5 1 7 2 8 3 10 4 14 5 20 6 28 7 38 8 50 9 72
Use the table below to answer the following questions. Output Fixed Cost Variable Cost Total Cost...
Use the table below to answer the following questions. Output Fixed Cost Variable Cost Total Cost Average Fixed Cost Average Variable Cost Average Total Cost Marginal Cost 0 10 1 20 7 2 20 32 6 3 20 41 6.67 13.67 4 20 40 5 20 75 6 20 132 3.33 25.33 7 237 2.86 31 33.86 8 20 356 9 20 515 2.22 57.22 10 20 700 2 A) What is the firm’s minimum efficient scale? B) How much...
Workers Quantity of Production Fixed Cost Variable Cost Total Cost Average Fixed Cost Average Variable Cost...
Workers Quantity of Production Fixed Cost Variable Cost Total Cost Average Fixed Cost Average Variable Cost Average Marginal Cost Total Cost 0 0 1 20 2 60 3 140 4 200 5 240 6 260 7 268 8 272 The table above shows the production and cost schedule for producing t-shirts. Each worker is paid $250 per day and the total fixed cost of capital is $1000. T-shirts can be sold at a local store for $15. a) Use this...
Fill in the following table with the missing cost information. Output Total Fixed Cost Total Variable...
Fill in the following table with the missing cost information. Output Total Fixed Cost Total Variable Cost Total Cost Average Fixed Cost Average Variable Cost Average Total Cost Marginal Cost 1 — — $650 — — — — 2 — — $740 — — — — 3 — — — — — — $120 4 — $510 — — — — — 5 $500 — — — — — $180
Use the table below to answer questions about a firm’s hiring decision.       Labor (workers) Output...
Use the table below to answer questions about a firm’s hiring decision.       Labor (workers) Output (units) Total Cost ($) 0 0 $50 1 15 $60 2 27 $70 3 37 $80 4 45 $90 5 50 $100 What is the total cost when the marginal product of labor is 10? Choose one:A.   $60 B.   $70 C.   $20D.   $90 E.   $30F.   $40G.   $10H.   $50I.   $80 J.   $100   What is the total variable cost when the marginal product of labor is...