Question

Consider a company considering a project that will last three years A. If the project will...

Consider a company considering a project that will last three years

A. If the project will return $30 million a year for the next three years and the cost interest rate is 8%, what is the value of these cash flows?

B. Suppose instead the project will return $20 million at the end of the first year and at the end of the second year, and $40 million at the end of the third year. No other be Guaranteed. If the opportunity cost interest rate is 8%. What is the value of these cash flows?

C. Why are the values of the cash flows different even though there is a total amount being guaranteed in both projects?

EXPLAIN YOUR ANSWERS

Homework Answers

Answer #1

A.

Cash flows per year = $30 Million

R = 8%

n = 3 years

Present value of the cash flows = 30*(1-1/(1+R)^n)/R = 30*(1-1/1.08^3)/.08

Present value of the cash flows = $77.31 Million

B.

When for year 1 and 2, the cash flows are $20 Million each and $40 million in year 3,

Present value of the cash flows = 20/1.08 + 20/1.08^2 + 40/1.08^3

Present value of the cash flows = $67.42 Million

C.

Difference is due to the following reasons:

1. first case, there is a total of $90 Million in 3 years and in second case, it is total of $80 millions in 3 years. So, there will difference in final value.

2. In first case there is uniformity in cash flows per year, but in second case biggest cash flow comes in the last 3rd year. It makes a bigger discounting to the biggest cash flow, causing reduced present value of the total cash flows. It makes a big difference.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Opportunity Cost of Capital for a firm considering a project is best described as: A....
The Opportunity Cost of Capital for a firm considering a project is best described as: A. The return that investor must be guaranteed to consider approving the project. B. The return that makes the cash flows equivalent to a government bond (The risk-free rate) C. The best available expected return in the market for projects of similar risk and duration.
There are 2 projects that the company is considering: Project A costs 10,000 to implement today,...
There are 2 projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1; 4,000 at the end of year 2; 6,000 at the end of year 3 Project B’s initial cost is 12,000, and subsequent cash flows are 6,000 per year for 3 years. WACC is 8% for both projects. a. calculate NPV and IRR for each project and decide which one to...
Bob’s Burgers is considering a project with an initial cost of $8 million that would produce...
Bob’s Burgers is considering a project with an initial cost of $8 million that would produce cash flows of $1.5 million the first year, $2 million the second, and $2.5 million per year for the final two years. If the required return is 11.3%, should Bob do the project?
A company is considering a new project that will cost $750,000. The project is expected to...
A company is considering a new project that will cost $750,000. The project is expected to generate positive cash flows over the next four years in the amounts of $300,000 in year one, $325,000 in year two, $150,000 in year three, and $180,000 in year four. The required rate of return is 8%. What is the project’s payback period? 2.60 years 2.83 years 2.63 years 2.33 years 2.50 years
A firm wants to buy a machine that will last three years. Its initial cost is...
A firm wants to buy a machine that will last three years. Its initial cost is $3 million. It can borrow the money at 5% interest per year. They estimate they will increase revenues by $500,000 in the first year, $500,000 in the second year and $2.5 million in the third year. What is the Net Present Value of this investment if they use a discount rate of 4%?
Green Forest Industrial is considering a project that would last for 3 years and have a...
Green Forest Industrial is considering a project that would last for 3 years and have a cost of capital of 12.74 percent. The relevant level of net working capital for the project is expected to be 17,000 dollars immediately (at year 0); 5,000 dollars in 1 year; 36,000 dollars in 2 years; and 0 dollars in 3 years. Relevant expected operating cash flows and cash flows from capital spending in years 0, 1, 2, and 3 are presented in the...
Middlefield Motors is considering a project that would last for 3 years and have a cost...
Middlefield Motors is considering a project that would last for 3 years and have a cost of capital of 17.12 percent. The relevant level of net working capital for the project is expected to be 20,000 dollars immediately (at year 0); 13,000 dollars in 1 year; 37,000 dollars in 2 years; and 0 dollars in 3 years. Relevant expected operating cash flows and cash flows from capital spending in years 0, 1, 2, and 3 are presented in the following...
There are two projects that the company is considering: Project A costs -10,000 to implement today,...
There are two projects that the company is considering: Project A costs -10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1; 1,500 at the end of year 2; 2,100 at the end of year 3; and 3,400 at the end of year 4. Project B's initial cost is -10,000, and subsequent cash flows are 2,500 per year for five (5) years. WACC is 6% for both projects. a. Calculate NPV and...
Jackie Chang’s is considering a project with an initial cost of $231,400. the project will not...
Jackie Chang’s is considering a project with an initial cost of $231,400. the project will not produce any cash flows for the first 2 years. starting in year 3, the project will produce cash flows of $144,000 a year for 3 years. this project is risky, so the firm has assigned it a discount rate of 16.5%. what’s the projects net present value? a. $2,335.56 b. $122,585.57
Orange Valley Recycling is considering a project that would last for 3 years and have a...
Orange Valley Recycling is considering a project that would last for 3 years and have a cost of capital of 15.69 percent. The relevant level of net working capital for the project is expected to be 16,000 dollars immediately (at year 0); 8,000 dollars in 1 year; 39,000 dollars in 2 years; and 0 dollars in 3 years. Relevant expected operating cash flows and cash flows from capital spending in years 0, 1, 2, and 3 are presented in the...