Max has contracted with Lew to have his house painted. The contract specifically stated that the job was to be completed by August 25. Lew completes the job on August 26. Max has suffered no loss due to the delay. The job was otherwise done exactly to all contract requirements and specifications. If Max sues Lew for breach of contract due to the missed completion date and if the courts were to award damages, what type of damages would most likely be awarded?
Multiple choice: Which one is correct?
punitive damages
consequential damages
restitution
nominal damages
Option D.