16. Use the Benefit-cost ratio analysis to determine the best alternative. Each alternative has a 6-year useful life. Assume 15% MARR. Show all work.
A B C
First cost $560 $340 $120
Annual Benefit $140 $100 $40
Salvage $40 $0 $0
you should compare the alternatives at the end
Please rate the answer
Answer
B-C ratio is calculated by dividng present value of all the
benefits by the present value of all the costs .
PV of benefits can be calculated by using P/A factor for 6
year
The salvage value will be discounted for 6 years
Project A
PV of costs = 560 $
PV of benefits = 140 * P/A(15%,6) + 40/(1.15)6
= 140*3.7845 + 40/2.3130
=529.83 + 17.29
=547.12 $
B/C ratio = 547.12 /560
= .977
Project B
PV of costs = 340 $
PV of benefits = 100 * P/A(15%,6)
= 100 * 3.7845
=378.45
B/C ratio = 378.45/340
= 1.113
Project C
PV of costs = 120$
PV of benefits = 40 * P/A(15%,6)
= 40* 3.7845
=151.38
B/C ratio = 151.38 /120
= 1.2615
Project C has the highest B/C ratio . Project C should be selected
. Project B might be selected if the sufficient amount is left
after Project C to be invested. Project A is inviable as the ratio
is less than 1.
Get Answers For Free
Most questions answered within 1 hours.