Question

Case study A firm operates at full capacity to manufacture 10,000 items a year of a...

Case study

A firm operates at full capacity to manufacture 10,000 items a year of a product to meet market demand. It is anticipated the demand will increase in the following few years. The firm is considering two alternatives to meet the anticipated increase in demand. The planning horizon is 4 years, and the MARR is 10% p.a.

Alternative 1: Use the existing machine and cater for the increase in demand by using overtime. The costing data for this option are shown below.

Present value of the existing machine:                                                                                    $10,000

Fixed annual operating cost (regardless of the quantity manufacture):                     $10,000

Added value per item up 10,000 items                                                                                    $5

Added value per item for all items above 10,000 (due to overtime costs) $4

Salvage value of the machine after 4 years                                                                            $0

Note: Added value per item is the contribution per item, i.e. Gross profit which is the difference between selling price and direct cost.

Alternative 2: Sell the existing machine and replace it with a new automatic machine with higher capacity. Due to productivity improvements, the added value per item will be $8. The costing data for this option are shown below.

Initial cost of the new machine:                                                                                 $50,000

Fixed annual operating cost (regardless of the quantity manufacture):                     $30,000

Added value per item                                                                                                                     $8

Salvage value of the machine after 4 years                                                                            $0

The firm feels confident about the costing data except the fixed annual operating cost for the new machine. It feels that the estimated fixed annual operating cost for the new machine may be subject to error.

In addition, the estimated increase in demand is also subject to error.

Advise the firm the option that it should adopt under different scenarios, i.e. changes in fixed operating cost of the new machine and changes in annual demand for the product.

I have found the answer for these question in the site already, but I need the answer in a more complete way, with the formulas, more explained, once I need to answer that as a study case.
Above are some information about the answer that I do need to provide.

Assessment of your work will take into account

➢ Relevance of your answer to the question or task set

➢ Clarity of expression

➢ Logical planning and sequence

➢ Overall presentation of the work and grammar.

Homework Answers

Answer #1

Answer:
Given that
A firm operates at full capacity to manufacture 10,000 items
The planning horizon is N= 4 years
MARR is 10% p.a.
therefore MARR i= 10/100
       = 0.1
we have to check the difference in present value for 10000 items plus one item after those 10000 units for both the alternates.

Alternate 1
= -P-P(P/A,i,N)+P*ITEM(P/A,i,N)+OVERTIME(P/A,i,N)
= -P-P((1+i)^N -1)/(i.(1+i)^N)+P*(PER ITEM)((1+i)^N -1)/(i.(1+i)^N)+OVER TIME((1+i)^N -1)/(i.(1+i)^N)

= -10000- 10000( (1.1)4-1)/0.1(1.1)4 +50000( (1.1)4-1)/0.1(1.1)4 +4( (1.1)4-1)/0.1(1.1)4

= -10000- 31698.65+158493+12.64

= 116807

ALternate
= -P-F(F/A,i,N)(P/A,i,N) + P*ITEM(P/A,i,N)+OVERTIME(P/A,i,N)
= -P-F((1+i)^N -1)/(i.(1+i)^N)+P*(PER ITEM)((1+i)^N -1)/(i.(1+i)^N)+OVER TIME((1+i)^N -1)/(i.(1+i)^N)

= -50000- 30000( (1.1)4-1)/0.1(1.1)4 +80000( (1.1)4-1)/0.1(1.1)4 +8 ( (1.1)4-1)/0.1(1.1)4

=-50000-95095.96+253589.23+25.28

=108518

Hence alternative1 is greater than alternative 2
therefore choose alternative1.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Martin-Beck Company operates a plant in St. Louis with an annual capacity of 30,000 units....
The Martin-Beck Company operates a plant in St. Louis with an annual capacity of 30,000 units. Product is shipped to regional distribution centers located in Boston, Atlanta, and Houston. Because of an anticipated increase in demand, Martin-Beck plans to increase capacity by constructing a new plant in one or more of the following cities: Detroit, Toledo, Denver, or Kansas City. The estimated annual fixed cost and the annual capacity for the four proposed plants are as follows: Proposed Plant Annual...
A small firm has developed a new machine to manufacture steel canisters. The machine is a...
A small firm has developed a new machine to manufacture steel canisters. The machine is a considerable improvement over the ones currently available in the market in terms of size and noise suppression. If the company’s management decides to manufacture this new machine, it is almost certain that the larger firms in the industry will copy the design and take the majority of the market through price competition. As such, management is also considering the possibility of entering into a...
The annual demand of a good is 10,000 ​units, the fixed cost of placing an order...
The annual demand of a good is 10,000 ​units, the fixed cost of placing an order is ​$90 and the annual cost of storing an item is ​$30. The same​ order, Q, is placed at regular intervals throughout the​ year, and the firm waits for stock levels to reduce to zero before ordering new stock. ​(a) Obtain an​ expression, for the total ordering cost​ C, in terms of Q. ​(b) Work out how many items should be ordered each time...
1. The Hunter Company uses the high-low method to estimate the cost function. Year-to-date information for...
1. The Hunter Company uses the high-low method to estimate the cost function. Year-to-date information for 2020 is provided below: Machine-hours Labor Costs January 400 $10,000 February 280 $ 6,800 March 380 $10,050 April 250 $ 7,300 May 320 $ 9,525 What can Hunter expect the total cost to be when 300 machine-hours are used? Group of answer choices $9,406.25 $7,450.00 $8,200.00 $7,233.33 2. Southwestern Company needs 1,000 motors in its manufacture of automobiles. It can buy the motors from...
A computer server manufacturer currently has capacity and demand of 10,000 servers per year. It is...
A computer server manufacturer currently has capacity and demand of 10,000 servers per year. It is considering two options to increase its capacity. The first option is to add 10,000 units of capacity to the plant, this will incur an annualized (need to pay in each period) fixed cost of 10,000,000 plus 500 labor cost per server. The second option is to outsource the production (anything above the capacity) to an independent manufacturer at a cost of 2,000 for each...
A product is being manufactured on a machine that has a book value of $10,000 (20...
A product is being manufactured on a machine that has a book value of $10,000 (20 years ago it was purchased for $50,000). The costs of the product are as follows: Item Unit Costs Labor, direct 4.00 Labor, variable indirect 5.00 Other variable overhead 2.50 Fixed overhead 2.50 Total 14.00 In the past year 10,000 units were produced and sold for $10 per unit. It is expected that the old machine can be used indefinitely in the future and that...
A 5-year project requires an investment of 10,000 at inception and maintenance express at the beginning...
A 5-year project requires an investment of 10,000 at inception and maintenance express at the beginning of each year. The maintenance expense is 300 for the first year and is anticipated to increase 6% each year thereafter. Projected annual returns from the project are 3,000 at the end of the first year and decrease by 100 per year thereafter. Calculate the NPV for a cost of capital of 7%. I am not sure where I am going wrong but I...
Problem 5-4 A small firm intends to increase the capacity of a bottleneck operation by adding...
Problem 5-4 A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two alternatives, A and B, have been identified, and the associated costs and revenues have been estimated. Annual fixed costs would be $37,000 for A and $31,000 for B; variable costs per unit would be $9 for A and $11 for B; and revenue per unit would be $19.      a. Determine each alternative’s break-even point in units. (Round your answer...
Oakmont Company has an opportunity to manufacture and sell a new product for a four-year period....
Oakmont Company has an opportunity to manufacture and sell a new product for a four-year period. The company’s discount rate is 17%. After careful study, Oakmont estimated the following costs and revenues for the new product: Cost of equipment needed $ 165,000 Working capital needed $ 67,000 Overhaul of the equipment in year two $ 10,000 Salvage value of the equipment in four years $ 13,000 Annual revenues and costs: Sales revenues $ 320,000 Variable expenses $ 155,000 Fixed out-of-pocket...
Oakmont Company has an opportunity to manufacture and sell a new product for a four-year period....
Oakmont Company has an opportunity to manufacture and sell a new product for a four-year period. The company’s discount rate is 17%. After careful study, Oakmont estimated the following costs and revenues for the new product: Cost of equipment needed $ 165,000 Working capital needed $ 67,000 Overhaul of the equipment in year two $ 10,000 Salvage value of the equipment in four years $ 13,000 Annual revenues and costs: Sales revenues $ 320,000 Variable expenses $ 155,000 Fixed out-of-pocket...