Question

A chemical engineer is planning to start a starch manufacturing unit. He prepared a project plan,...

A chemical engineer is planning to start a starch manufacturing unit. He prepared a project plan, identified the activities and the expected time required for each activity. A project activity chart with expected time of all activities is given in the following table.

a. Draw the network diagram showing all activities as listed in the table.

b. Find out the critical path and earliest expected time duration for the project.

Activity Time required (Hrs) Predecessors
1 20
2 14 1, 3
3 12
4 14
5 20 3
6 10 2,4
7 8 5,6

Homework Answers

Answer #1

a)

Activity     Activity Earliest Earliest Latest Latest Slack
Time Start, ES Finish, EF Start, LS Finish, LF (LS-ES)
1 20 0 20 0 20 0
2 14 20 34 20 34 0
3 12 0 12 8 20 8
4 14 0 14 20 34 20
5 20 12 32 24 44 12
6 10 34 44 34 44 0
7 8 44 52 44 52 0

b)

Critical path includes the activities with zero slack.

So, critical path is 1-2-6-7 as shown by red circles in the above network.

Earliest completion time=time required to complete activities on critical path

=20+14+10+8=52 hours

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
The R&D Department is planning to bid on a large project for the development of a...
The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes.  The accompanying table shows the activities, times, and sequences required: Activity Immediate Predecessor Optimistic Most Likely Pessimistic A - 3 6 8 B A 2 4 4 C A 1 2 3 D C 6 7 8 E B,D 2 4 6 F B 6 10 14 G E, F 1 2 4 H F 3 6 9 I...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can start at the same time, however Activity C can only start once Activity A ends Activity D can only start once Activity B and Activity C ends Activity E and Activity F can only start once Activity D ends The following table shows Durations for each activity Activity Duration (weeks) A 5 B 4 C 2 D 7 E 3 F 2 a. Draw...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT