Question

What is the life cycle cost of a vehicle under the following scenario: Initial cost is...

What is the life cycle cost of a vehicle under the following scenario: Initial cost is $50,000. Maintenance cost is $2500/yr. The maintenance increases $500/yr starting in year 5. The car is sold in year 10 for $10,000. The interest rate is 4%/yr. PLEASE INCLUDE A CASH FLOW DIAGRAM or I will not rate. Thank you!

Homework Answers

Answer #1
Year Initial cost Annual cost Resale value Net Cash flow Discount factor Present value
0 -50000 -50000 1.00000 -50000.00
1 -2500 -2500 0.96154 -2403.85
2 -2500 -2500 0.92456 -2311.39
3 -2500 -2500 0.88900 -2222.49
4 -2500 -2500 0.85480 -2137.01
5 -2500 -2500 0.82193 -2054.82
6 -3000 -3000 0.79031 -2370.94
7 -3500 -3500 0.75992 -2659.71
8 -4000 -4000 0.73069 -2922.76
9 -4500 -4500 0.70259 -3161.64
10 -5000 10000 5000 0.67556 3377.82
Present value -68866.79

Life cycle cost = 68867

Cash flow diagram

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compare the purchase of a boat, using annual vs monthly payments. The boat costs $50,000. The...
Compare the purchase of a boat, using annual vs monthly payments. The boat costs $50,000. The interest rate is 12%. The loan is for 5 years. You sell it in either case for $20,000. Define the life cycle cost of the boat purchase and the annual outlay for payments under each scenario. PLEASE INCLUDE A CASH FLOW DIAGRAM or I will not rate. Thank you!
Compare the purchase of a boat, using annual vs monthly payments. The boat costs $50,000. The...
Compare the purchase of a boat, using annual vs monthly payments. The boat costs $50,000. The interest rate is 12%. The loan is for 5 years. You sell it in either case for $20,000. Define the life cycle cost of the boat purchase and the annual outlay for payments under each scenario. PLEASE INCLUDE A CASH FLOW DIAGRAM or I will not rate. Thank you!
Choose between the following two scenarios. Base your decision on Annualized Worth AW. Show the details...
Choose between the following two scenarios. Base your decision on Annualized Worth AW. Show the details of the calculation for full credit. A         Initial Cost 120,000      I = 6 %    Revenue per year 80,000               Maintenance Expenses First year 4000   grows each year by 1500 ( G = 1500 / yr)                 Operating Expenses     First year 6000 grows each year by 500.            Planning Horizon 20 years.   Salvage Value 10,000. B          Initial Cost 400,000    I = 3%                 Revenue     First...
show cash flow diagram A Capitalized cost was computed to be ₱2M. The structure includes some...
show cash flow diagram A Capitalized cost was computed to be ₱2M. The structure includes some additional expenses of ₱100,000 at the beginning of the year for the next 15 years, a renewal cost of ₱200,0000 would occur in which the expected life of the structure is 5 years. Another cost to consider starting at the end of the tenth year for 20 years is expected amounting to ₱10,000. If the interest rate is 9% per year, determine the perpetual...
Apple is considering a project with a three-year life and an initial cost of $90,000. The...
Apple is considering a project with a three-year life and an initial cost of $90,000. The discount rate for the project is 16 percent. The firm expects to sell 1,400 units on the last day of each year. The cash flow per unit is $35. The firm will have the option to abandon this project following the sales on the last day of year 2 at which time the project's assets could be sold for an estimated $45,000. The firm's...
You are installing a fire pump as a part of an existing apartment building. The initial...
You are installing a fire pump as a part of an existing apartment building. The initial purchase price and installation cost of the pump is $17,000. The pump has an annual maintenance cost of $1,500 which includes all maintenance, inspection, and testing. At the end of the 10 year life of the pump, it is expected to have a salvage value of $2,500. Draw the cash flow and the simplified cash flow diagram. When you were born, your grandparents put...
Western Industrial Products is considering a project with a five-year life and an initial cost of...
Western Industrial Products is considering a project with a five-year life and an initial cost of $300,000. The discount rate for the project is 11 percent. The firm expects to sell 2,600 units a year. The cash flow per unit is $30. The firm will have the option to abandon this project at the end of year three (after year three's sales) at which time the project's assets could be sold for an estimated $55,000. The firm should abandon the...
Western Industrial Products is considering a project with a five-year life and an initial cost of...
Western Industrial Products is considering a project with a five-year life and an initial cost of $320,000. The discount rate for the project is 9 percent. The firm expects to sell 2,800 units a year. The cash flow per unit is $40. The firm will have the option to abandon this project at the end of year three (after year three's sales) at which time the project's assets could be sold for an estimated $65,000. The firm should abandon the...
Western Industrial Products is considering a project with a five-year life and an initial cost of...
Western Industrial Products is considering a project with a five-year life and an initial cost of $320,000. The discount rate for the project is 9 percent. The firm expects to sell 2,800 units a year. The cash flow per unit is $40. The firm will have the option to abandon this project at the end of year three (after year three's sales) at which time the project's assets could be sold for an estimated $65,000. The firm should abandon the...
Western Industrial Products is considering a project with a four-year life and an initial cost of...
Western Industrial Products is considering a project with a four-year life and an initial cost of $268,000. The discount rate for the project is 14.5 percent. The firm expects to sell 2,200 units on the last day of each year. The cash flow per unit is $50. The firm will have the option to abandon this project after one year at which time the project's assets could be sold for an estimated $225,000. The firm should abandon the project immediately...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT