Question

Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...

Question 5: Forecasting (8 p)

The table below shows the demand (in units per quarter) of a specific product in the past three years.

Quarter

Year

1

2

3

4

2015

350

254

176

228

2016

367

258

169

236

2017

342

250

166

228

Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units.

Question 6: DRP (8 p)

A central DC supplies a specific product to the regional DCs A and B.

A has a planned order release of 150 units in week 3, 4 and 5.

B has a planned order release of 125 units in week 2, 3 and 4.

Complete the DRP schedule of the central DC (below). You don’t have to consider a safety stock.

Lead time = 2 weeks

Lot size = 250 (or multiple)     

Week

1

2

3

4

5

Gross requirements

-

In transit

-

250

-

-

-

-

Projected available

50

Planned order release

-

Question 7: Optimal lot size (6 p)

The expected quantity required for a certain component is 6,400 units per year. It is made for 16 euros each (value), within the own factory. The machine in question has a production speed of 25,600 units per year. Set a year equal to 320 days. The setup costs are 80 euros per changeover. The inventory costs per item are 10% per year over the value of the component. Calculate the optimal lot size, that minimizes the total costs per year.

Question 8: Service level (4 + 8 p)

A store orders products from its supplier 10 times a year (on average). The expected annual demand is 4,000 units. Set a year equal to 50 weeks.

The store manages the stock with the order point system. The weekly demand is normally distributed with a standard deviation of 15 units. The supplier has a delivery time of 2.5 weeks. It costs the store 12 euros to keep 1 product in stock for a year.

a. Calculate the order point if the store wants to achieve a service level SL1 of 94%.

b. The store is taken over by an ambitious chain that only wants to accept an expected shortage of 4 units per year. Calculate the total inventory costs per year for this new situation.

Question 9: Case (2 x 10 p)

Read the text about Valcon in the appendix and answer the following questions. Do not quote extensively from the text, but use your own words (with the correct terms) as well as your knowledge and understanding (that you acquired through studying theory).

a. One of the measures taken was to improve the RCCP. Explain what RCCP is and why it had to be improved in this company.

b. Valcon has not only improved the RCCP, but also the scheduling (the text explains to some degree how this has been done). As you know, scheduling is a part of Production activity control.

Imagine you would be the consultant. Give two advices (that are not found in the text) how Production activity control can be applied in a company like this.

Appendix. Valcon: production planning improvement for a manufacturer

The client of Valcon is a leading farm equipment manufacturer, with a significant presence in the Europe and American markets. Due to low cost production and also because of increased awareness about scientific farming in India, the client set up a manufacturing facility in India during the last decade. Almost up to 70% of the volume is for the export market.

The challenge

The business model of the client was “make to order”. With the delivery lead time of at least three months from the date of receipt, and a large number of SKUs (close to 500) in one production setup, the client was struggling to meet the customer commitments. The main challenge was the poor production planning methodology prevalent in the company. The client approached Valcon for improving production planning and also developing a system which gives more clarity on customer deliveries and raw material procurement from the suppliers.

The solution                                                                                                                                                                 Valcon identified some complexities in the business nature of the client like large number of SKUs and product families, with each SKU having a different production routing and process. There were no dedicated machines allocated based on the product family. Rough cut capacity planning (RCCP), production scheduling and material planning were identified for improving the planning process. In order to improve rough cut capacity planning, the average demand was established for each SKU. Cycle times were measured and the machines required to meet average demand were computed.

Machines were dedicated based on product families and their respective demands. To ensure optimum utilization of bottleneck resource production, the scheduling process with respect to the bottleneck process was adopted. Valcon identified the bottleneck in the production routing and the production lead time required to meet the customer order. Capacities were booked in the bottleneck process and all operations at the preceding manufacturing stations were planned for smoother flow. As a result of good RCCP and scheduling, the clarity on material requirement improved. This helped in timely placement of production order based on lead time for supply by the respective supplier.

The result                                                                                                                                                                                 The outcome of RCCP process provided better clarity to the client in terms of determining average number of machines required for each product family, clarity on processes which have to be outsourced due to lack of capacity and also a roadmap for future investment to alleviate the bottleneck and hence enhance the capacity. Production scheduling allowed the client to have better clarity about operations, throughput time and also ability to forecast activities relating to machine maintenance.

Homework Answers

Answer #1

Solution (5):

Based on the given information, let us first calculate the % demand in each of the quarter. The formula that we are going to use for that is Total Demand in a given quarter / Total Demand in a year. Based on this the values are:

Quarter/Year 1 2 3 4
2015 34.7% 25.2% 17.5% 22.6%
2016 36.4% 25.6% 16.8% 23.4%
2017 33.9% 24.8% 16.5% 22.6%
Average 35.0% 25.2% 16.9% 22.9%

Now, as the total demand for year 2018 is given as 1,040. Using this the demand for:

Quarter 1 = Total Demand*Average for quarter 1 = 1,040*35% = 364.

Quarter 2 = Total Demand*Average for quarter 2 = 1,040*25.2% = 262.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of a specific product in the past three years. Quarter Year 1 2 3 4 2015 350 254 176 228 2016 367 258 169 236 2017 342 250 166 228 Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units.
Ace Manufacturing produces commercial lawnmowers units in batches. the company estimates the demand for the year...
Ace Manufacturing produces commercial lawnmowers units in batches. the company estimates the demand for the year is 10,000 units. It costs about $80 to set up the manufacturing process, and the carrying cost is about 70 cents per unit per year. When the production process has been set up, 120 lawnmowers units can be made daily. The demand during the production period is approximately 60 units per day. The company operates its production area 167 days per year and includes...
Question 2 A car engine manufacturer has the following production goals for the next year: Engine...
Question 2 A car engine manufacturer has the following production goals for the next year: Engine Quantity Machine Req’s V6 2000 6hrs V8 1500 10hrs V12 100 20hrs If all three engines can be produced by the same machines and each of the manufacturer’s machines operate for 2400 hours per year, how many machines are required for the above product mix? Question 3 A manufacturing operation has three stages: •Stage 1 Capacity: 400 units/hr •Stage 2 Capacity: 300 units/hr •Stage...
Please show the Work Question 1 A lawnmower manufacturer has the following data: Unit revenue: $200...
Please show the Work Question 1 A lawnmower manufacturer has the following data: Unit revenue: $200 Unit variable cost: $75 Fixed costs: $400,000 (annually) Given the above data, what are: The profit/loss for annual production = 5000? The annual production at the break-even point? The profit/loss for annual production = zero? Question 2 A car engine manufacturer has the following production goals for the next year: Engine Quantity Machine Req’s V6 2000 6hrs V8 1500 10hrs V12 100 20hrs If...
(Operations Management) The annual demand of an appliance company is 8000 units. The production capacity is...
(Operations Management) The annual demand of an appliance company is 8000 units. The production capacity is 200 units per day. Each time production starts, it costs the company $120 to move materials into place, reset the assembly line, and clean the equipment. The holding cost of a refrigerator is $50 per year. The current production plan calls for 400 refrigerators to be produced in each production run. Assume 250 working days per year. a) Compute the daily demand of this...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule for the last quarter of the year. The Brazilian Division had planned to sell 70,400 units during the year, but by September 30 only the following activity had been reported: Units Inventory, January 1 0 Production 72,800 Sales 64,000 Inventory, September 30 8,800 The division can rent warehouse space to store up to 29,300 units. The minimum inventory level that the division should carry...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule for the last quarter of the year. The Brazilian Division had planned to sell 68,860 units during the year, but by September 30 only the following activity had been reported: Units Inventory, January 1 0 Production 72,400 Sales 62,600 Inventory, September 30 9,800 The division can rent warehouse space to store up to 29,200 units. The minimum inventory level that the division should carry...
The Indigo Girls Company has the capacity to produce 90,000 units per year. Normal production and...
The Indigo Girls Company has the capacity to produce 90,000 units per year. Normal production and sales are 75,000 units per year. The normal selling price is $15 per unit. At the 75,000 unit level of activity, unit costs are as follows: Direct material $2.25 per unit Variable Overhead $1.50 per unit Fixed Overhead $2.00 per unit ($150,000 total) Direct Labor $1.75 per unit Variable Selling $1.00 per unit Fixed Selling $1.20 per unit ($80,000 total) A special one-time customer...
Question 1 Towers Industries Co. produces a vast range of screws. The company is introducing five...
Question 1 Towers Industries Co. produces a vast range of screws. The company is introducing five new products for its consumer market. A twinfast screw (SKU XT175) is a type of screw that can be driven twice as fast as a normal screw with the same pitch. A wood screw (SKU OH624) is a screw with a sharp point designed to attach two pieces of wood together. A security screw (SKU HV502) is a type of screw whose head is...
Question 3 A retail outlet sells holiday decorations for $10 per bag. The cost of the...
Question 3 A retail outlet sells holiday decorations for $10 per bag. The cost of the product is $8 per bag. Any units not sold during the selling season can be sold for $5 a bag at the end of the season. Assume that demand for these decorations is normally distributed with a mean of 500 and standard deviation of 100 bags. a. What is the recommended order quantity? b. What is the probability that at least some customers will...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT