The table shows the cost schedule for Eclipse Enterprise.
Output (Unit) |
Total Fixed Cost (RM) |
Total Variable Cost (RM) |
Total Cost (RM) |
Average Fixed Cost (RM) |
Average Variable Cost (RM) |
Average Cost (RM) |
Marginal Cost (RM) |
0 |
20 |
||||||
1 |
50 |
||||||
2 |
70 |
||||||
3 |
86 |
||||||
4 |
110 |
||||||
5 |
150 |
||||||
6 |
206 |
||||||
7 |
270 |
Question: Complete the following cost schedule for Eclipse Enterprise.
My answer table below: (if my answer table wrong, pls correct it. If possible show calculate getting answer. Thanks)
Output (Unit) |
Total Fixed Cost (RM) |
Total Variable Cost (RM) |
Total Cost (RM) |
Average Fixed Cost (RM) |
Average Variable Cost (RM) |
Average Cost (RM) |
Marginal Cost (RM) |
0 |
20 |
0 |
20 |
0 |
0 |
0 |
0 |
1 |
20 |
30 |
50 |
20 |
30 |
50 |
30 |
2 |
20 |
50 |
70 |
10 |
25 |
35 |
20 |
3 |
20 |
66 |
86 |
6.67 |
22 |
28.67 |
16 |
4 |
20 |
90 |
110 |
5 |
22.5 |
27.5 |
24 |
5 |
20 |
130 |
150 |
4 |
26 |
30 |
40 |
6 |
20 |
186 |
206 |
3.33 |
31 |
34.3 |
56 |
7 |
20 |
250 |
270 |
2.86 |
35.71 |
38.57 |
64 |
Answer;
Your calculations are absolutely correct.
Total Cost= Fixed Cost+Variable Cost
Marginal Cost= Change in Cost/Change in quantity
Fixed Cost is always fixed during the production.
Average Fixed Cost= Fixed Cost/Quantity
Variable Cost= Total Cost-Fixed Cost
Average Variable Cost= Variable Cost/ Quantity
Average Total cost=Total Cost/Quantity
Output | Total Fixed Cost | Total Variable Cost | Total Cost | Average Fixed Cost | Average Variable Cost | Average Cost | Marginal Cost |
0 | 20 | 0 | 20 | 20/0=0 | 0 | 20/0=0 | - |
1 | 20 | 30 | 50 | 20/1=20 | 30/1=30 | 50/1=50 | (30-0)/(1-0)=30 |
2 | 20 | 50 | 70 | 10 | 25 | 35 | 20 |
3 | 20 | 66 | 86 | 6.67 | 22 | 28.67 | 16 |
4 | 20 | 90 | 110 | 5 | 22.5 | 27.5 | 24 |
5 | 20 | 130 | 150 | 4 | 26 | 30 | 40 |
6 | 20 | 186 | 206 | 3.33 | 31 | 34.3 | 56 |
7 | 20 | 250 | 270 | 2.86 | 35.71 | 38.57 | 64 |
Get Answers For Free
Most questions answered within 1 hours.