Question

The table shows the cost schedule for Eclipse Enterprise. Output (Unit) Total Fixed Cost (RM) Total...

The table shows the cost schedule for Eclipse Enterprise.

Output (Unit)

Total Fixed Cost

(RM)

Total Variable Cost (RM)

Total Cost (RM)

Average Fixed Cost (RM)

Average Variable Cost (RM)

Average Cost

(RM)

Marginal Cost

(RM)

0

20

1

50

2

70

3

86

4

110

5

150

6

206

7

270

Question: Complete the following cost schedule for Eclipse Enterprise.      

My answer table below: (if my answer table wrong, pls correct it. If possible show calculate getting answer. Thanks)

Output (Unit)

Total Fixed Cost

(RM)

Total Variable Cost (RM)

Total Cost (RM)

Average Fixed Cost (RM)

Average Variable Cost (RM)

Average Cost

(RM)

Marginal Cost

(RM)

0

20

0

20

0

0

0

0

1

20

30

50

20

30

50

30

2

20

50

70

10

25

35

20

3

20

66

86

6.67

22

28.67

16

4

20

90

110

5

22.5

27.5

24

5

20

130

150

4

26

30

40

6

20

186

206

3.33

31

34.3

56

7

20

250

270

2.86

35.71

38.57

64

Homework Answers

Answer #1

Answer;

Your calculations are absolutely correct.

Total Cost= Fixed Cost+Variable Cost

Marginal Cost= Change in Cost/Change in quantity

Fixed Cost is always fixed during the production.

Average Fixed Cost= Fixed Cost/Quantity

Variable Cost= Total Cost-Fixed Cost

Average Variable Cost= Variable Cost/ Quantity

Average Total cost=Total Cost/Quantity

Output Total Fixed Cost Total Variable Cost Total Cost Average Fixed Cost Average Variable Cost Average Cost Marginal Cost
0 20 0 20 20/0=0 0 20/0=0 -
1 20 30 50 20/1=20 30/1=30 50/1=50 (30-0)/(1-0)=30
2 20 50 70 10 25 35 20
3 20 66 86 6.67 22 28.67 16
4 20 90 110 5 22.5 27.5 24
5 20 130 150 4 26 30 40
6 20 186 206 3.33 31 34.3 56
7 20 250 270 2.86 35.71 38.57 64
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The table below refers to the production cost of Syarikat Sonata Enterprise. Quantity Fixed Cost Variable...
The table below refers to the production cost of Syarikat Sonata Enterprise. Quantity Fixed Cost Variable Cost Total Cost Average Total Cost Marginal Cost 0 100 0 - - 1 20 2 35 3 50 50 4 100 150 37.5 0 5 -10 6 100 -12 Based on the table, answer the following questions. a)  Complete the table above. (1/2 mark for each correct answer = Total 10 marks) b)  Calculate the Average Variable Cost (AVC) and Average Fixed Cost (AFC) at...
Table 16-4 This table shows the demand schedule, marginal cost, and average total cost for a...
Table 16-4 This table shows the demand schedule, marginal cost, and average total cost for a monopolistically competitive firm. Quantity Price Marginal Cost Average Total Cost   0 $50 -- --   1 $45 $30 $40   2 $40 $24 $32   3 $35 $14 $26   4 $30 $10 $22   5 $25 $12 $20   6 $20 $32 $22   7 $15 $50 $26   8 $10 $74 $32   9   $5 $104 $40 10   $0 $140 $50 Refer to Table 16-4. What price will this firm charge...
Use the total cost(TC) schedule that is presented in the the table below to calculate average...
Use the total cost(TC) schedule that is presented in the the table below to calculate average total cost, average variable cost, average fixed cost and marginal cost when output (Q) is equal to 6 Q TC 0 5 1 7 2 8 3 10 4 14 5 20 6 28 7 38 8 50 9 72
In the table below you will find a schedule of a firm’s fixed cost and variable...
In the table below you will find a schedule of a firm’s fixed cost and variable cost. Complete the table by computing total cost, average fixed cost, average variable cost, average total cost, and marginal cost.                  Total Total Average Average Average Total fixed variable    Total      fixed variable total Marginal product cost cost cost cost cost cost     cost     0 80 0 1 80 100 2 80 180 3 80 240 4 80 320 5 80 440 6 80 600...
complete the table below: Output Total Cost Variable Cost FIxed Cost Marginal Cost 0 50 1...
complete the table below: Output Total Cost Variable Cost FIxed Cost Marginal Cost 0 50 1 60 2 75 3 100 4 150 5 225 6 400
Total Product Total Fixed Cost Total Variable Cost 0 $150 $   0 1 150 50 2...
Total Product Total Fixed Cost Total Variable Cost 0 $150 $   0 1 150 50 2 150 75 3 150 105 4 150 145 5 150 200 6 150 270 7 150 360 8 150 475 9 150 620 10 150 800 Based on the cost data given in the accompanying table, which of the price-quantity tables correctly represents the firm's short-run supply schedule? (a) (b) (c) (d) P Qs P Qs P Qs P Qs $20 1 $20 0...
Table 16-5 This table shows the demand schedule, marginal cost, and average total cost for a...
Table 16-5 This table shows the demand schedule, marginal cost, and average total cost for a monopolistically competitive firm. Quantity Price Marginal Cost Average Total Cost 0 $30 -- -- 1 $24   $2 $32 2 $18   $4 $18 3 $12 $6 $14 4 $6   $8 $10 5 $0 $10 $10 Refer to Table 16-5. How much profit will this firm earn at the monopolistically competitive price? A) $0 B) $5 C) $12 D) $16
Fill in the blanks in the following table: output total cost total fixed cost total variable...
Fill in the blanks in the following table: output total cost total fixed cost total variable cost average fixed cost average variable cost average total cost marginal cost 100 4500 3500 1000 35 10 45 200 9 8 300 9.50 400 7300 8.75 500 4890 16.78 600 6000 10 700 5 12.50 800 12150 15.19 A) complete the table B) do your numbers in the table illustrate the expected relation between average variable cost and marginal cost? between average total...
Total revenue; Explicit cost; Implicit cost; Price; Fixed cost; Variable cost; Accounting cost; Economic cost Using...
Total revenue; Explicit cost; Implicit cost; Price; Fixed cost; Variable cost; Accounting cost; Economic cost Using the above concepts, write an equation for accounting profit (5 points) Using the table below answer the questions 8-10 and show your work. Quantity Total Cost Fixed Cost Variable Cost Marginal Cost Average Fixed Cost Average Variable Cost Average Total Cost 0 $50 $50 $0 -- -- -- -- 1 $150 A B C D E F 2 $270 G H I J K...
According to the following table, what is the fixed cost, marginal cost, and average total cost...
According to the following table, what is the fixed cost, marginal cost, and average total cost of producing the 4th unit? Output Total Cost 0 1 2 3 4 5 $20 $30 $35 $50 $80 $115
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT