A public project with social discount rate of 6% has determined that its initial costs will be spread out over the first 2 years of construction. They will be $10,000,000 in year 0, $15,000,000 in year 1, and $5,000,000 in year 2. Beginning in year 3 and continuing until year 22, the project will have an annual operating expense of $1,000,000. In addition, the city government sponsoring the project will receive $100,000 per year in revenue because of the project. The private businesses in the area expect to gain $4,000,000 per year in new business because of the project in years 3 - 22. However, the construction will disrupt several local business during year 1 and 2 resulting in a loss of $750,000 per year during those two years for those businesses. What is the present worth of the net costs/revenues in this project (Enter in the box to the nearest dollar with no dollar sign)?
PW ($) = PW of all benefits - PW of initial costs - PW of all costs
= - 10,000,000 - 15,000,000 x P/F(6%, 1) - 5,000,000 x P/F(6%, 2) + 100,000 x P/A(6%, 22) + (4,000,000 - 1,000,000) x P/A(6%, 20) x P/F(6%, 2) - 750,000 x P/A(6%, 2)
= - 10,000,000 - 15,000,000 x 0.9434** - 5,000,000 x 0.8900** + 100,000 x 12.0416** + 3,000,000 x 11.4699** x 0.8900** - 750,000 x 1.8334**
= - 10,000,000 - 14,151,000 - 4,450,000 + 1,204,160 + 30,624,633 - 1,375,050
= 1,852,743
**From P/A and P/F Factor tables