Question

Note: Please answer the second question (b) Should we choose Projects A, C, D or Projects...

Note: Please answer the second question

(b) Should we choose Projects A, C, D or Projects A, B, D. Explain

The following is a list of four projects that Capital Corporation must choose from for the coming year: Project Project Price Annual Net Inflows

A                   700,000                      118,861

B                   670,000                      109,039

C                 184,000                       32,549

D                  273,000                      48,305

Given a uniform rate of interest of 9% and a uniform life of the projects of 10 years each, calculate the NPVs of each Project (To calculate NPV, calculate the Present Value of a 10 year annuity, and subtract the project price. You can use Excel to do this calculation - it is the easiest process. Open excel, go to formula button (fx), select category financial, select PV or present value, Rate is the rate of interest (9% or .09) NPER is the number of years (10) and Pmt is negative of the yearly Net Inflows (Its negative because excel assumes that Pmt means you are making payments, whereas in this problem you are receiving net revenues). Once you input that for each project excel will give you the Present Values for each project. Once you get the present values or PV subtract from each the Project Price to get the NPV.

PV

FC

Npv

-118861

$762,809.21

700000

$62,809.21

-109039

$699,774.98

670000

$29,774.98

-32549

$208,888.34

184000

$24,888.34

-48305

$310,004.96

243000

$67,004.96

(b) Should we choose Projects A, C, D or Projects A, B, D. Explain

Homework Answers

Answer #1

Now if we try to decide which combination of projects to choose we can think of one method ie B/C

Ratio of (PW of Benefit/PW of Cost)-1 if this number comes >=9% we will choose that project

BC for A=(PW of Benefit/PW of Cost)-1=8.97%

BC for B=(PW of Benefit/PW of Cost)-1=4.44%

BC for C=(PW of Benefit/PW of Cost)-1=13.52%

BC for D=(PW of Benefit/PW of Cost)-1=27.57%

Hence BC for B is much smaller than that of other BC's and less than 9%

Hene projects A,C,D are to be chosen

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
. The following is a list of four projects that Capital Corporation must choose from for...
. The following is a list of four projects that Capital Corporation must choose from for the coming year: Project Project Price Annual Net Inflows A 700,000 118,861 B 670,000 109,039 C 184,000 32,549 D 273,000 48,305 (a) Given a uniform rate of interest of 9% and a uniform life of the projects of 10 years each, calculate the NPVs of each Project (To calculate NPV, calculate the Present Value of a 10 year annuity, and subtract the project price....
Annual cash inflows that will arise from two competing investment projects are given below:      Year...
Annual cash inflows that will arise from two competing investment projects are given below:      Year Investment A Investment B 1 $ 4,000       $7,000       2 5,000       6,000       3 6,000      5,000       4 7,000       4,000       Total $22,000       $22,000       The discount rate is 12%. Required: Compute the present value of the cash inflows for each investment. Each investment opportunity will require the same initial investment. (Use Microsoft Excel to calculate present values. Do not round intermediate calculations.) Investment A: Item RATE...
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the...
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the firm’s production capacity. The relevant cash flows for the projects are shown in the following table. The firm’s cost of capital is 15%. PROJECT B PROJECT C YEAR Cash Flow Cash Flow 0 350000 50000 1 45000 24000 2 65000 22000 3 65000 19500 4 440000 14600 a) Calculate the period back of each project, assess its acceptability, and indicate which project is best,...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow is $50,000 for each project. Project A results in cash inflows of $15,625 at the end of each of the next five years. Project B results in one cash inflow of $99,500 at the end of the fifth year. The required rate of return of Ace Inc. is 10 percent. Ace Inc. should invest in: a. ​Project B because it has no cash inflows...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow is $50,000 for each project. Project A results in cash inflows of $15,625 at the end of each of the next five years. Project B results in one cash inflow of $99,500 at the end of the fifth year. The required rate of return of Ace Inc. is 10 percent. Ace Inc. should invest in: a.Project B because it has no cash inflows in...
Which of the following statement is correct? a. A firm should never accept the independent projects...
Which of the following statement is correct? a. A firm should never accept the independent projects having NPVs greater than zero. b. All the answers are incorrect. c. Because the net present value method does not factor in the time value of money, nor the cash flows after the payback period, its usefulness is limited. d. Mutually exclusive projects are the projects that do not have the same task and therefore they do not compete with each other. e. The...
The company that just hired you is trying to choose between two innovation projects using net...
The company that just hired you is trying to choose between two innovation projects using net present value. The two projects have the following cash flows: Project 1: year 1 - $1,500; Year 2 - $2,000; Year 3 - $5,000; Year 4 - $3,000; Project 2: year 1 - $5,000; Year 2 - $3,000; Year 3 - $1,500; Year 4 - $2,000; Interest rate: 10% Assignment a: Calculate the NPVs for each project Assignment b: Which of these projects should...
Suppose you can choose between the following projects. Calculate Net Present Value for each and make...
Suppose you can choose between the following projects. Calculate Net Present Value for each and make a decision concerning which is best. Assume the relevant interest rate is 5%. I. A die cast machine that costs $1,000.00 and provides an income stream of $200.00 per year for six years. II. A plastic molding machine that costs $1,000.00 and provides an income stream of $250.00 per year for five years. Better project is: Its NPV is: B) Suppose you are offered...
Question 3 Consider two projects, A and B, associated with the following expected cash flow sequences...
Question 3 Consider two projects, A and B, associated with the following expected cash flow sequences Year Project A Project B 0 -950 -950 1 400 240 2 400 240 3 450 240 4 0 240 5 0 240 6 0 240 You are acting as the Chief Financial Officer of a firm. Suppose you face a capital rationing constraint such that you have a limit of 950 currency units in your budget. Your firm’s weighted average cost of capital...
QUESTION 5 (20 Marks) Note: Where applicable, use the present value tables provided in APPENDICES 1...
QUESTION 5 Note: Where applicable, use the present value tables provided in APPENDICES 1 and 2 that appear after REQUIRED Use the information given below to calculate the following: 5.1 Payback Period of both projects (answers expressed in years and months). 5.2 Accounting Rate of Return of Project A (answer expressed to two decimal places). 5.3 Net Present Value (NPV) of both projects (amounts rounded off to the nearest Rand). 5.4 Profitability Index of Project B (answer expressed to two...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT