Question

In September​ 2015, a 3.45 megawatt​ cooling, heating, and power​ (CHP) system was placed in into...

In September​ 2015, a 3.45 megawatt​ cooling, heating, and power​ (CHP) system was placed in into operation for Southeast Regional Hospital with 360 beds. The CHP system was part of a new​ 20,000 sq. ft. central utility plant that provided the​ 800,000 sq. ft.​ health-care facility with​ cooling, heating and power. By centralizing all of the utilities in one​ location, the hospital accrued significant energy​ savings, as well as improved maintenance efficiency. The financial facts related to the project are summarized as

Installed​ cost: ​$2.6 million

Annual energy cost​ savings: ​$797,000

Annual​ O&M costs: ​$213,000

Project service​ life:17 years

Salvage​ value: ​$200,000

At an interest rate of 11%, what is the net savings per dollar​ invested?

Homework Answers

Answer #1

Installed​ cost: ​2600000

Annual energy cost​ savings: ​797,000

Annual​ O&M costs: ​213,000

Project service​ life:17 years

Salvage​ value: ​200,000

At an interest rate of 11%

Net savings per dollar invested = PV of savings / (First cost + PV of costs - PV of salvage value)

= [797000 * (P/A, 11%,17)] / [(2600000 + 213000 * (P/A, 11%,17) -200000 * (P/F, 11%, 17)]

= [797000 * 7.54879439] / [(2600000 + 213000 * 7.54879439 -200000 * 0.169632616 ]

= 6016389.129 / [ 2600000 + 1607893.205 - 33926.5232]

= 1.4183

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT