Question

in pw analysis for a single project, the project should be implemented only when npw of...

in pw analysis for a single project, the project should be implemented only when npw of benefits is greater than 0

Homework Answers

Answer #1

True.

Present Worth Analysis of Equal-Life Alternatives
One alternative:
Calculate the PW using the MARR. If PW > 0, the
MARR is met or exceeded and the alternative is
financially viable.
Two or more alternatives:
Calculate the PW of each alternative using the MARR.
Select the alternative with the PW value that is
numerically largest, that is, less negative and more
positive, indicating a lower PW of cost cash flows or
larger PW of net cash flows of receipts minus
disbursements.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
make a benefit/cost analysis by finding B/C for a project with a total PW of cost...
make a benefit/cost analysis by finding B/C for a project with a total PW of cost of $6,859, annual benefits of $ 1,723, annual disbenefits of $487, interest rate of 6% and life of 6 years
1)For the below ME alternatives , which machine should be selected based on the PW analysis....
1)For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 25,529 30000 10000 Annual cost, $/year   8,565                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A= 2)For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First...
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR is 10%. Machine A Machine B Machine C First cost, $ 15000 30000 13,435 Annual cost, $/year   16,207                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- PW for machine C =
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 14,991 Annual cost, $/year 8,930 6,000 4,000 Salvage value, $ 4,000   5,000 1,000 Life, years ( A= 3, B= 6. C= 2) Answer the below questions : C- PW for machine C =?
Describe cost-benefits analysis and explain when is should be used and when it should be avoided.
Describe cost-benefits analysis and explain when is should be used and when it should be avoided.
What should you consider when you conduct capital budgeting analysis? a when the cash flows are...
What should you consider when you conduct capital budgeting analysis? a when the cash flows are made b the riskiness of the project c how much the initial investment is for the project d all of the above e a and b only
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less...
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less than 1; greater than 1 Less than 0; greater than 0 Greater than 1; less than 1 Greater than 0; less than 0 Equal to 1; Greater than 1 Equal to 0; Greater than 0
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater...
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater than WACC; less than WACC Greater than MIRR; less than MIRR Less than WACC; greater than WACC Less than MIRR; greater than MIRR Less than 0; Greater than 0 Greater than 0; Less than 0
Perform a benefit /cost analysis for the following usage cost projects having the same life time...
Perform a benefit /cost analysis for the following usage cost projects having the same life time of 5 years and interest rate of 2% by finding the incremental benefits/costs in steps one after the other. You have to write only the final value of incremental benefits/costs in the required answer field. The three projects have the following values, all calculated in PW form: Project 1 : benefits = $51,138 and cost =$14,831 Project 2 : benefits = $79,480 and cost...
A mining company is considering a new project. Because the mine has received a permit, the...
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $10.33 million at Year 0 to mitigate the environmental Problem, but it would not be required to do so. Developing the mine (without mitigation) would require an initial outlay of $63 million, and the expected cash inflows would be $21 million per year for...