(You should produce a graph that features (a) an average total cost (ATC) curve; (b) a marginal cost (MC) curve; and (c) a line representing the hypothetical price of $9 per ride. The graph should be labeled appropriately, have a reasonable scale on the vertical (cost) axis and horizontal (quantity) axis. When you have completed the graph in your spreadsheet program, copy and paste it here.)
Q |
TC |
0 |
27 |
1 |
30 |
2 |
32 |
3 |
35 |
4 |
38 |
5 |
42 |
6 |
48 |
7 |
57 |
8 |
68 |
Please give ratings it will be appreciable thank you
ATC = TC/ Q
MC = change in TC due one unit increase in output
so
MC (Q=1) = TC ( Q=1) - TC(Q=0) (30 - 27=3)
MC (Q=2) = TC ( Q=2) - TC(Q=1) (32 - 30=3)
MC (Q=3) = TC ( Q=3) - TC(Q=2) (35-32=3)
Q | TC | ATC | MC | P |
0 | 27 | |||
1 | 30 | 30 | 3 | 9 |
2 | 32 | 16 | 2 | 9 |
3 | 35 | 11.67 | 3 | 9 |
4 | 38 | 9.5 | 3 | 9 |
5 | 42 | 8.4 | 4 | 9 |
6 | 48 | 8 | 6 | 9 |
7 | 57 | 8.14 | 9 | 9 |
8 | 68 | 8.5 | 11 | 9 |