You are a hotel manager and you are considering four projects that yield different payoffs, depending upon whether there is an economic boom or a recession. The potential payoffs and corresponding payoffs are summarized in the following table.
Project |
Boom (60%) |
Recession (40%) |
A |
$30 |
$20 |
B |
-$10 |
$50 |
C |
$40 |
-$30 |
D |
$20 |
$40 |
Which project should the manager invest in? Explain in detail how you would present your selection to the firm.
If the manager were able to adopt project C and D simultaneously, is that a better option than the one selected in part a? Explain.
The project would be selected on the basis of the return that it generates
Expected return for all the aforesaid options:
A =[30*60%+20*40%]
=18+8
=26
B = [-10*60%+50*40%]
= -6+20
=14
C= [40*60%+(-30)*40%]
=24+(-12)
=12
D=[20*60%+40*40%]
=12+16
=28
As we see the maximum Return is given Option D hence it will be selected
Most importantly if the manager was able to adopt project C and D simultaneously then too it would be viable enough to sail through the recession as the total return in this case would be $40 (12+28).
Get Answers For Free
Most questions answered within 1 hours.