Question

Corporation XYZ is considering the following projects. If their MARR is 15% and they have $165,000...

Corporation XYZ is considering the following projects. If their MARR is 15% and they have $165,000 available to spend, which projects should they select?

Project Investment Present Worth
A $50,000 $10,200
B $35,000 ($7,650)
C $15,000 $8,200
D $100,000 $6,300

Homework Answers

Answer #1

Answer :-

here based on present worth analysis the corporation should invest which has highest present worth value.

=> First of all , they should invest $50000 in project A because it's have highest npv $10200.

=> after that , they should invest $15000 in project C because it's npv is positive $8200

=> and last , they should invest remaining $100000 in project D which has positive npv amount.

here, they should not invest in project B since it will be loss making project because it's npv is negative.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Tempura Inc. is considering two projects. Project A requires an investment of $50,000. Estimated annual receipts...
Tempura Inc. is considering two projects. Project A requires an investment of $50,000. Estimated annual receipts for 20 years are $20,000; estimated annual costs are $12,500. An alternative project, B, required an investment of $75,000, has annual receipts for 20 years of $28,000, and has annual costs of $18,000. Assume both projects have a zero salvage value and that MARR is 12%/year. Please show cash flow diagram and please don't use excel functions. Thank you! a. What is the present...
"A firm is considering two projects with the following cash flows and internal rates of return....
"A firm is considering two projects with the following cash flows and internal rates of return. If the firm's MARR is 12%, should it select project A, project B, or neither? It cannot select both the projects. Project A Year 0: -7 Year 1: 0 Year 2: 9 Project B Year 0: X Year 1: 0 Year 2: 32 The IRR for Project A is 13.39% and that of Project B is 20.29%. Enter the net present worth of the...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects are summarized below. Year ManBearPig Project Cash Flow Flying Car Cash Flow 0 -$100,000    -$200,000    1 25,000 50,000 2 25,000 50,000 3 50,000 80,000 4 50,000 100,000 The two projects have the same risk. At what cost of capital would the two projects have the same net present value (NPV)? A. 10.03% B. -24.45% C. 2.86% D. 13.04% E. 15.90%
Dorati Inc. is considering two mutually exclusive projects.  Dorati used a 15% required rate of return to...
Dorati Inc. is considering two mutually exclusive projects.  Dorati used a 15% required rate of return to evaluate capital expenditure projects.  If the two projects have the costs and cash flows shown below, determine the NPV for each. Year                             Project S                                   Project T    0                                -$70,000                                   -$100,000    1                                  $50,000                                      $60,000    2                                  $60,000                                      $70,000    3                                                                                    $80,000                        4                                                                                    $90,000
You are considering two independent projects both of which have been assigned a discount rate of...
You are considering two independent projects both of which have been assigned a discount rate of 15% percent. Based on the project NPV, what is your recommendation concerning these projects? Project A Project B Year Cash Flow Year Cash Flow 0 -$40,000 0 -$51,173 1 $35,000 1 $18,400 2 $27,000 2 $14,750 You should accept both projects. You should reject both projects. You should accept project B and reject project A. You should accept project A and reject project B....
Bam Corporation is considering the following independent projects for the coming year. Their target capital structure...
Bam Corporation is considering the following independent projects for the coming year. Their target capital structure is 60 percent debt and 40 percent equity. The after-tax cost of debt is 6 percent and the cost of equity is 15 percent.                                                                                                             Expected                                                                      Required                                Rate of                          Risk Project              Investment                               Return                         Level A                   $13 million                                17%                              High B                     16 million                                9                                 Low C                     25 million                                 14                               Average D                  ...
The management of Penfold Corporation is considering the purchase of a machine that would cost $300,000,...
The management of Penfold Corporation is considering the purchase of a machine that would cost $300,000, would last for 5 years, and would have no salvage value. The machine would reduce labor and other costs by $70,000 per year. The company requires a minimum pretax return of 12% on all investment projects. Click here to view Exhibit 13B-1 and Exhibit 13B-2 to determine the appropriate discount factor(s) using the tables provided. The net present value of the proposed project is...
Gamma Company is planning to invest in several of eight (8) projects. Unfortunately, it faces a...
Gamma Company is planning to invest in several of eight (8) projects. Unfortunately, it faces a range of constraints such as budgetary, number of projects that it can supervise, and the relationship among projects (contingent and/or duplicative). The Company is seeking your assistance in selecting the projects that will maximize its Net Present Worth given the set of constraints. Projects Initial Cost NPW A 250,000 40,000 B 300,000 35,000 C 225,000 50,000 D 400,000 70,000 E 350,000 65,000 F 275,000...
Two government projects have the following benefit profiles: Project A Project B Initial Investment Cost 100,000...
Two government projects have the following benefit profiles: Project A Project B Initial Investment Cost 100,000 100,000 Benefits, Year 1 0 40,000 Benefits, Year 2 0 40,000 Benefits, Year 3 80,000 40,000 Benefits, Year 4 80,000 40,000 Which of the following statements is accurate? a. Because the combined benefits of the two projects over the four years each equals 160,000, the net present value of the projects will be equal. b. Because the sum of benefits (160,000) exceeds the investment...
[The following information applies to the questions displayed below.] The following capital expenditure projects have been...
[The following information applies to the questions displayed below.] The following capital expenditure projects have been proposed for management's consideration at Scott, Inc., for the upcoming budget year: Use Table 6-4 and Table 6-5. (Use appropriate factor(s) from the tables provided. Round the PV factors to 4 decimals.) Project Year(s) A B C D E Initial investment 0 $ (61,000 ) $ (72,000 ) $ (137,000 ) $ (150,000 ) $ (288,000 ) Amount of net cash return 1 12,800...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT