Question

5. (a) A 500 MW nuclear power generation station has been built in an area spending...

5. (a) A 500 MW nuclear power generation station has been built in an area spending US$ 200 million. To meet the local demand, additional 300 MW power is necessary. Estimate the cost of the new plant (300 MW). Assume Cost-Capacity factor of 0.8.

(b) A power generation company has built 75 MW solar electricity generation plant with US$ 1.4 million in a remote area. To meet the local demand, additional 100 MW power is necessary. Estimate the cost of the new plant to meet the local demand (100 MW). Assume standard Cost-Capacity factor.

Homework Answers

Answer #1

C2 = Required cost of Plant 2 with capacity Q2

C1 = Known cost of Plant 1 with capacity Q1

Q2 = Known capacity of Plant 2

Q1 = Known capacity of Plant 1

x = Cost capacity factor for technology of plant 2 and 1

C2/C1 = (Q2/Q1)^x

A.

C1 = US$ 200 million
Q2 = 300MW
Q1 = 500MW
x = 0.8

As per the above formula, the cost of Plant 2 with 300MW capacity = US$132.9 million

B.

C1 = US$1.4 million
Q2 = 100MW
Q1 = 75MW
x = 1

As per the above formula, the cost of Plant 2 with 300MW capacity = US$ 1.87 million

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
B. A regional electric utility currently relies on natural gas for power generation. It has 200...
B. A regional electric utility currently relies on natural gas for power generation. It has 200 Mw of natural gas capacity that is running on an average of 30 percent efficiency. It is studying options for supplying additional power to its customers. It has all of the following options: Coal:   A 50 megawatt (Mw) coal plant with a capital cost of $50 million and operating costs of $5 million per year plus the cost of coal. The coal plant would...
1. A regulated investor-owned electric utility currently generates 12 million Mwh per year with a total...
1. A regulated investor-owned electric utility currently generates 12 million Mwh per year with a total rate base, including transmission and distribution assets, of $10 billion. Its operating costs are $200 million annually. If the regulatory agency allows a 10 percent rate of return on the rate base, what is the regulated price of electricity, and the utility's annual earnings? 2. The utility projects its annual electricity demand to grow by an additional 7 million Mwh to 19 Mwh per...
In this exercise we will consider two coal-fired power plants and a solar thermal plant, in...
In this exercise we will consider two coal-fired power plants and a solar thermal plant, in order to compare their power densities, i.e., their power output vs. the amount of land they occupy. This method of comparison of diverse forms of renewable and non-renewable energy systems was pioneered by Vaclav Smil of the University of Manitoba in Canada. The first coal plant is highly efficient and is optimally located, next to a mine that supplies high-quality coal from a thick...
An electrical utility is experiencing a sharp power demand in a certain local area, and you...
An electrical utility is experiencing a sharp power demand in a certain local area, and you consider two alternatives. Each is designed to provide enough capacity during the next 25 years, and both will consume the same amount of fuel, so fuel cost is not considered in the analysis. The first alternative: Increase the generating capacity now so that the ultimate demand can be met without additional expenditures later. An investment of $25 million would be needed, and the plant...
he coal mining industry has been hard-hit by environmental regulations. Recently, however, a combination of increased...
he coal mining industry has been hard-hit by environmental regulations. Recently, however, a combination of increased demand for coal and new pollution reduction technologies has led to an improved market demand for coal. WHC has just been approached by Mid-Cen Electric Company with a request to supply coal for its electric generators for the next eight years. WHC does not have enough excess capacity at its existing mines to guarantee the contract. The company is considering opening a strip mine...
How failing power utility is fuelling South Africa’s economic crisis South Africa’s state power utility Eskom...
How failing power utility is fuelling South Africa’s economic crisis South Africa’s state power utility Eskom is the biggest challenge facing the country. Mess up Eskom, and you mess up the country. In addition, it looks as though key players are doing just that. The past two weeks will be remembered as the start of a cataclysmic economic crisis caused by the failure of three powerful men to spend enough time in a room to find a comprehensive solution that...
Exploring Innovation in Action Power to the People – Lifeline Energy Trevor Baylis was quite a...
Exploring Innovation in Action Power to the People – Lifeline Energy Trevor Baylis was quite a swimmer in his youth, representing Britain at the age of 15. So it wasn’t entirely surprising that he ended up working for a swimming pool firm in Surrey before setting up his own company. He continued his swimming passion – working as a part-time TV stuntman doing underwater feats – but also followed an interest in inventing things. One of the projects he began...
read PV Versus Diesel: A Cost-Benefit Analysis in the Nexus of Food and Fuel below and...
read PV Versus Diesel: A Cost-Benefit Analysis in the Nexus of Food and Fuel below and then answer the following questions: - What is the problem? - What are the alternatives? - What are the base case assumptions? - What measures do you suggest to compare the alternatives? PV Versus Diesel: A Cost-Benefit Analysis in the Nexus of food and fuel. U.S. Army provides field rations to forward troops. After Desert Storm and Desert Shield, where some troops ate packaged...
Please show me how to apply CVP analysis for this case study. FLY ASH BRICK PROJECT:...
Please show me how to apply CVP analysis for this case study. FLY ASH BRICK PROJECT: FEASIBILITY STUDY USING CVP ANALYSIS S. K. Mitra and Shubhra Hajela wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be transmitted, photocopied, digitized or otherwise reproduced in any...
Fueling Indonesians: Window of Opportunity or Regret? Kerosene is widely used as cooking fuel by Indonesian...
Fueling Indonesians: Window of Opportunity or Regret? Kerosene is widely used as cooking fuel by Indonesian households, with an annual usage of 10 million Kiloliters. It is a major subsidized fuel for household cooking, where its usage is over sixty percent of the 230 million population. The subsidy program costs the government heavily, where it amounts up to U.S.$4 billion a year. As the practice tends to bleed government expenditures quite heavily, the Indonesian government is embarking on a change...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT