The cookie company in the mall hires only labor to produce
cookies. The workers are paid $70 per day, and the cost of renting
the space in the mall is $300 per day.
Number of workers | Daily output (cookies) |
1 | 200 |
2 | 400 |
3 | 600 |
4 | 700 |
The daily fixed costs of production are
Choose one:A. $300 .B. $370 .C.
$140 .D. $70 .E. $0.
The labor cost per day of hiring two workers
is $ .
The total cost per day when three workers are hired
is $ .
The marginal product per day of the fourth worker
is cookies.
Fixed cost of production = $300
Cost of per labour =$70
1) Daily fixed cost of production is cost of rent so fixed cost of production =$300
Correct answer is A
2) Labour cost of hiring two worker per day (2×$70) =$ 140
3) total cost of hiring three worker per day labour cost(3×$70) =$ 210
Fixed cost =$300
Total cost =$210+ $300 = $510
4) Marginal productivity at 4th labour
= TP at 4 worker - TP at 3 worker
= 700-600
= 100
Marginal productivity at 4th worker =$100