Question

1. One of the team members on the project wants the team to take no more...

1. One of the team members on the project wants the team to take no more user stories per sprint to get things done faster. As an adaptive leader, what should you do?

Select one:

a. Listen and explain that the member should discuss this with the product owner

b. Say no right away

c. Listen, but explain the concept of a self-directed team

d. Negotiate so that the member doesn’t cause any interruptions

2. Adaptive Leadership includes:

Select one:

a. Identifying the problem and finding a middle ground

b. Meeting the Troops and creating a personal link

c. Making objectives clear, but avoiding micromanaging

d. B and C

3. Which of the following shows a viable product or service as a prototype?

Select one:

a. Definition of done

b. User Stories

c. Strategy to accomplish goals

d. Wireframe

4. Emotional Intelligence is the ability to mirror another in order to enhance communication

Select one:

True

False

5. Your team is collocated and is discussing what they learned, what they are working on and solutions to their issues. Not everyone is contributing to the discussion, however, information is being internalized. This is known as

Select one:

a. Tribal knowledge

b. Osmotic communication

c. Tacit knowledge

d. Team knowledge

6. To negotiate well within a project

Select one:

a. Contexts of both parties should be understood

b. A solution to satisfy both parties is the best

c. Searching for an agreeable alternative is always warranted

d. All of the above

Homework Answers

Answer #1

Hi There,

I have bolded the correct options. Hope it will help you!

1. One of the team members on the project wants the team to take no more user stories per sprint to get things done faster. As an adaptive leader, what should you do?

Select one:

a. Listen and explain that the member should discuss this with the product owner

b. Say no right away

c. Listen, but explain the concept of a self-directed team

d. Negotiate so that the member doesn’t cause any interruptions

Ans 1: a. Listen and explain that the member should discuss this with the product owner

2. Adaptive Leadership includes:

Select one:

a. Identifying the problem and finding a middle ground

b. Meeting the Troops and creating a personal link

c. Making objectives clear, but avoiding micromanaging

d. B and C

Ans 2: d. B and C

3. Which of the following shows a viable product or service as a prototype?

Select one:

a. Definition of done

b. User Stories

c. Strategy to accomplish goals

d. Wireframe

Ans 3: d. Wireframe

4. Emotional Intelligence is the ability to mirror another in order to enhance communication

Select one:

True

False

Ans 4: True

5. Your team is collocated and is discussing what they learned, what they are working on and solutions to their issues. Not everyone is contributing to the discussion, however, information is being internalized. This is known as

Select one:

a. Tribal knowledge

b. Osmotic communication

c. Tacit knowledge

d. Team knowledge

Ans 5: d. Team knowledge

6. To negotiate well within a project

Select one:

a. Contexts of both parties should be understood

b. A solution to satisfy both parties is the best

c. Searching for an agreeable alternative is always warranted

d. All of the above

Ans 6: d. All of the above

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
11. Your executive team wants to cut the dividend this year because there has been a...
11. Your executive team wants to cut the dividend this year because there has been a temporary drop in earnings. Everyone expects that earnings will be back to normal next year. What should the team consider before making a final decision? Select one: a. The team should consider the dividend payout ratio. b. The team should consider the possibility that the dividend cut will be viewed as a negative signal regarding the longer term cash flow of the company, when...
Choose the right answer for these three question 1)If there are 20 people on a project...
Choose the right answer for these three question 1)If there are 20 people on a project team, how many two-way communication paths are there? a.45 b.90 c.190 d.110 2) Which of the following would not be a reasonable way to present an estimate if you are worried that someone will think you are padding effort or time? a.range of values b.point estimate with associated probability c.the pessimistic estimate d. none of the above 3) Which of the following activity-based estimating...
QUESTION 1 Personas are useful in the a product costing stage b product design phase c...
QUESTION 1 Personas are useful in the a product costing stage b product design phase c the entire life cycle d product testing phase QUESTION 2 Select all which are benefits of using personas. a they help in making design decisions. b they help identify user needs c they help define the software architecture d they make real users memorable for the design team QUESTION 3 A scenario is a one specific use for the interface b a typical day...
11. ____ quality validation is about validating the meanings of words in the model. Select one:...
11. ____ quality validation is about validating the meanings of words in the model. Select one: a. process b. pragmatic c. syntactic d. semantic 12. A business process redesign initiative is commonly seen as a: Select one: a. organic nature b. twofold challenge c. technical challenge d. socio-cultural challenge 13. An employee takes 3 months long service leave. Which component of the BPMS architecture is affected? Select one: a. worklist handler b. administration and monitoring tools c. external service d....
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
1- Magna Carta expressed the idea Select one: a. that only nobles need to consent to...
1- Magna Carta expressed the idea Select one: a. that only nobles need to consent to taxation. b. that the king is bound by the law. c. that all people should have the right of free speech. d. all of the above 2- Compared to the Benedictine monastaries of the 6th and 7th centuries, the Cluniac monasteries of the 11th century were more Select one: a. focused on missionary activity. b. democratic in their election of new abbots. c. interested...
ADVANCED AUDIT Part A. Multiple Choice 1. Professional skepticism is: Select one: Select one: a. Necessary...
ADVANCED AUDIT Part A. Multiple Choice 1. Professional skepticism is: Select one: Select one: a. Necessary for a quality control system b. Adherence to the professional code of ethics c. An attitude that includes a questioning mind, being alert to conditions which may indicate possible misstatement due to error or fraud, and a critical assessment of audit evidence. d. The application of relevant training, knowledge and experience, within the context provided by auditing, accounting and ethical standards, in making informed...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
1. An example of absolute logic is (SELECT ONE): A Framing after the slab is cured...
1. An example of absolute logic is (SELECT ONE): A Framing after the slab is cured B Installing windows before insulation C Painting before carpet is installed D Placing plumbing before electric 2. Which of the following project costs are relatively fixed in nature? (Choose all that apply) A Subcontracts B Overhead C Materials D Equipment E Labor 3. There will need to be more records generated and more details in the records in which type of contract (SELECT ONE)?...