Consider the following set of jobs to be scheduled for execution on a single CPU system....

Consider the following set of jobs to be scheduled for execution on a single CPU system.

Job

Arrival Time

Burst (msec)

Priority

A

0

6

3 (Silver)

B

1

2

1 (Diamond)

C

3

5

3 (Silver)

D

5

3

4 (Bronze)

E

7

2

2 (Gold)

  

(a)     Draw a Gantt chart showing First-Come-First-Served (FCFS) scheduling for these jobs. [3 Marks]

Answer (a)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer




(b)     Draw a Gantt chart showing preemptive PRIORITY scheduling. [3 Marks]

Answer (b)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer




(c)    Draw a Gantt chart showing Highest Response Ratio Next (HRRN) scheduling. [3 Marks]

Answer (c)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer

(d)     Draw a Gantt chart showing Round Robin (RR) (quantum = 4) scheduling. [3 Marks]

Answer (d)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer Answer

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following set of jobs to be scheduled for execution on a single CPU system....
Consider the following set of jobs to be scheduled for execution on a single CPU system. Job Arrival Time Burst (msec) Priority A 0 6 3 (Silver) B 1 2 1 (Diamond) C 3 5 3 (Silver) D 5 3 4 (Bronze) E 7 2 2 (Gold)    (a)     Draw a Gantt chart showing First-Come-First-Served (FCFS) scheduling , Premtive PRIORITY Sheduling, Highest Response ratio Next (HRRN) and Round Robin(quantum=4). I need this in half hour
I need a breakdown to perform in excel for numbers 7,8,9. I am unsure of how...
I need a breakdown to perform in excel for numbers 7,8,9. I am unsure of how I calculate the times. heres the data set and the questions. Calculate the probability that a flight will depart early or on time. Calculate the probability that a flight will arrive late. Calculate the probability that a flight departs late or arrives early. DEP_Delay ARR_Delay -4 0 -3 -3 0 -5 -7 -1 8 3 -1 -5 3 8 11 6 -6 0 -5...
Cork price: 16 10 15 10 17 11 14 13 11 14 11 16 18 16...
Cork price: 16 10 15 10 17 11 14 13 11 14 11 16 18 16 10 17 14 14 16 7 10 12 19 15 16 14 9 12 21 13 10 16 12 16 13 17 17 13 14 18 11 12 15 16 13 18 16 17 12 12 14 9 11 14 19 13 11 17 11 13 15 14 18 18 18 12 10 11 13 14 11 14 18 13 13 19 17 14...
Cork price: 16 10 15 10 17 11 14 13 11 14 11 16 18 16...
Cork price: 16 10 15 10 17 11 14 13 11 14 11 16 18 16 10 17 14 14 16 7 10 12 19 15 16 14 9 12 21 13 10 16 12 16 13 17 17 13 14 18 11 12 15 16 13 18 16 17 12 12 14 9 11 14 19 13 11 17 11 13 15 14 18 18 18 12 10 11 13 14 11 14 18 13 13 19 17 14...
Assuming that the population standard deviation is unknown, calculate the 95% confidence interval of the population...
Assuming that the population standard deviation is unknown, calculate the 95% confidence interval of the population mean. The following is the data. Calculating Process should be shown by Excel (Formulas). What formulas in statistics are used? 7 21 23 24 18 16 2 19 11 6 3 13 17 9 5 12 13 17 4 14 15 25 12 24 22 14 14 20 15 11 26 17 21 11 4 13 16 14 13 14 25 23 9 15...
Part A. In the past it has been found that the arrival time have a population...
Part A. In the past it has been found that the arrival time have a population mean value of μ = 13 and a population standard deviation of σ = 6.26. Using the given data, test whether this mean has changed. Use the critical value approach to test the hypothesis. The significance level alpha is set at 0.05 . The original data of time taken is given below. Show the process by using excel (Formulas). Part B. Test the hypothesis...
Bag Blue Orange Green Yellow Red Brown Total Number of Candies 1 7 23 9 11...
Bag Blue Orange Green Yellow Red Brown Total Number of Candies 1 7 23 9 11 4 6 60 2 16 16 4 7 9 4 56 3 14 14 3 10 5 11 57 4 13 14 7 8 8 6 56 5 18 12 7 10 5 7 59 6 12 9 11 9 8 8 57 7 15 16 6 6 6 8 57 8 15 17 8 4 6 7 57 9 12 14 10 5...
Dep Delay Arr Delay q1 -13 -9 q3 1 3 IQR 14 12 stdev 9.211846 9.660933...
Dep Delay Arr Delay q1 -13 -9 q3 1 3 IQR 14 12 stdev 9.211846 9.660933 negative 291 zero 39 positive 170 total (should be 500) 500 all data is for arrival data. please help me explain these can someone help me answer these questions and tell me how to put them in excel.thanx in advance 1.    Define a random variable (X) so that your chosen data set represents values of X. 2.    Is your chosen random variable discrete or...
6. Using the class data (see Blackboard file - "Class Survey Data - PSS-10 and GAS")...
6. Using the class data (see Blackboard file - "Class Survey Data - PSS-10 and GAS") calculate the correlation between the GAS – Goal disengagement and the GAS – Goal reengagement scores. Write the results in a statistical statement. 7. Using the class data calculate the correlation between the GAS – Goal disengagement and the PSS-10 scores. Write the results in a statistical statement. 8. Using the class data calculate the correlation between the GAS – Goal reengagement scores and...
USING C++ The purpose of this assignment is the use of 2-dimensional arrays, reading and writing...
USING C++ The purpose of this assignment is the use of 2-dimensional arrays, reading and writing text files, writing functions, and program planning and development. You will read a data file and store all of the input data in a two dimensional array. You will perform calculations on the data and store the results in the 2 dimensional array. You will sort the array and print the results in a report. Instructions You will read in the same input file...