Question

Why does the scheduling function depend on the planning function? Which one must be done first?...

  1. Why does the scheduling function depend on the planning function? Which one must be done first? Why?
  2. Describe what an activity estimated duration is. How is it determined?
  3. Why might a contractor prefer to state a project completion time in terms of number of days after the project starts rather than a specific date? Give some examples of instances when this would be appropriate.
  4. Why is it important to determine the critical path of a project? What happens if activities on this path are delayed? What happens if activities on this path are accelerated?
  5. From your experience, describe how you have used a project control process. If you did not use continual monitoring of the progress, how would this have helped improve the project’s success?
  6. Why should a project have a regular reporting period? Should all projects have the same reporting period? Why or why not? What types of data should be collected during each reporting period?
  7. Who can initiate changes to a project schedule? Describe why and when changes would occur in a project. How are the network diagram and schedule updated to reflect the changes?
  8. Describe how you would apply the four steps of schedule control to a project. If the project needs to be accelerated, what kinds of activities would be the primary focus? Why?
  9. Describe why it is necessary to develop a baseline budget for a project.
  10. List and describe items that should be included when estimating activity costs.
  11. What does the term reserve mean? Should a reserve amount be included in a project proposal? Explain your answer.What is the problem with making cost estimates too conservative or too aggressive?
  12. Describe the project budgeting process.
  13. Why is it necessary to track actual and committed costs once a project starts?
  14. What is the key to managing cash flow? How can this goal be accomplished?

Homework Answers

Answer #1

A schedule is a timetable for a plan•

The schedule cannot be established until theplan has been developed.

•The duration estimate for each activity is thetotal elapsed time for the work to be done,plus any associated waiting time.

•An activity’s duration estimate must bebased on the quantity of resources expectedto be used on the activity. The estimateshould be aggressive, yet realistic.

A Beta distribution using most likely,pessimistic, and optimistic times can beused.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1) how does the body correct for high blood pressure? Be descriptive (hormones etc.) 2) why...
1) how does the body correct for high blood pressure? Be descriptive (hormones etc.) 2) why is it important that the adrenal medulla is hardwired into the sympathetic nervous system and how this role is key to sympathetic response? 3) describe the production release of regulation of the catecholamines 4) why it is essential that catecholamines have such a short half-life when dealing with stress? what would happen if the half-life was increased? 5) explain the role of glucocorticoids in...
Project Management Scenario: You are a consultant with expertise in project management strategies. Select a possible...
Project Management Scenario: You are a consultant with expertise in project management strategies. Select a possible project management situation from your current or future professional experience. As a project management consultant, you are tasked with developing a project management plan for this project. Your goal is to maximize the time, resources and finances associated with the project in the best interests of the business/company. You will need to write a professional memo to the business/company owner describing the management of...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
After the scope has been approved, the next step in the process is determining what is...
After the scope has been approved, the next step in the process is determining what is required to complete the project successfully. This includes evaluating what needs to be procured, human resources needed, allocation of funds, as well as gaining an understanding of the support needed within the organization to deliver the project. This moves the project to the next phase: planning. This typically starts at the define stage and continues through most of the execution phase. The planning stage...
True Or False 1- Fixed costs should not be included in a flexible budget because they...
True Or False 1- Fixed costs should not be included in a flexible budget because they do not change when the level of activity changes. (       ) 2-To help assess how well a manager has controlled costs, actual costs should be compared to what the costs should have been for the actual level of activity. (       ) 3-The activity variance for revenue is favorable if the actual revenue for the period exceeds the revenue in the static planning budget. (      ...
Q1) Write a Python function partial_print, which takes one parameter, a string, and prints the first,...
Q1) Write a Python function partial_print, which takes one parameter, a string, and prints the first, third, fifth (and so on) characters of the strings, with each character both preceded and followed by the ^ symbol, and with a newline appearing after the last ^ symbol. The function returns no value; its goal is to print its output, but not to return it. Q2) Write a Python function called lines_of_code that takes a Path object as a parameter, which is...
What were the critical errors the RDH general manager made after the departure of HI in...
What were the critical errors the RDH general manager made after the departure of HI in 2000? At the urgent meeting of government officials and the RDH board, stakeholders decided to request the PHS leaders be allowed to address the RDH board and explain how they thought they could solve the RDH service problems. As the senior project manager for PHS, what issues would you want to discuss during this meeting? The RDH board has asked you to design a...
Your first assignment in your new position as assistant financial analyst at Caledonia Products is to...
Your first assignment in your new position as assistant financial analyst at Caledonia Products is to evaluate two new​ capital-budgeting proposals. Because this is your first​ assignment, you have been asked not only to provide a recommendation but also to respond to a number of questions aimed at assessing your understanding of the​ capital-budgeting process. This is a standard procedure for all new financial analysts at​ Caledonia, and it will serve to determine whether you are moved directly into the​...
II. I want you to make up a research project that you would like to do....
II. I want you to make up a research project that you would like to do. You will be guided through a step by step process of giving me all of the necessary information for a research plan. Be careful to answer each question completely using what you have learned about research design. You have decided to do a research project. A. Describe your project. What is your purpose, what question or questions are you trying to answer. B. What...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT