Question

In using PERT to find probabilities of project completion times, it is necessary to focus only...

In using PERT to find probabilities of project completion times, it is necessary to focus only on the critical path.

True of False

Homework Answers

Answer #1

Answer:

False

Explanation:

In using PERT to find probabilities of project completion times, it may be necessary for us to not focus only on the critical path(s), indeed, some researcher has suggested that expanding project resources to reduce variability of activities not on critical path can be effective element in project management but we may need also to compute these probabilities for noncritical paths especially those that have relatively large variances.

Please give thumbsup, if you like it. Thanks.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Find the critical path and the project completion time for the following list of activities. Calculate...
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10 I do not understand how...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4 5 4 B - 5 8 11 8 C A 1 2 3 2 D B 2 5 8 5 E B 4 6 8 6 F C,D 1 1 1 1 G E 3 4 5 4 H G,F 2 3 4 3 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
(UPDATED) Consider a project that requires the completion of 7 tasks, as follows: o Tasks A...
(UPDATED) Consider a project that requires the completion of 7 tasks, as follows: o Tasks A and B can begin simultaneously at the beginning (“time zero”). o Task C can only begin after task B is completed. o Task D can only begin after task A is completed. o Task E can only begin after task A is completed. o Task F can only begin after task E is completed. o Task G can only begin after tasks C and...
Good project management allows firms to efficiently create products and services for local markets and to...
Good project management allows firms to efficiently create products and services for local markets and to respond effectively to competitive local markets. True False The critical path is a continuous path through the project network that 1. Starts at the first activity in the project 2. Terminates at the last activity in the project 3. Includes only activities with a slack more than zero. True False To create goods and services, all organizations perform three functions: Marketing, Production/operations, and Finance/accounting....
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
PLEASE INDICATE CORRECT ANSWER ONLY! 1) The probability that a project will be completed by its...
PLEASE INDICATE CORRECT ANSWER ONLY! 1) The probability that a project will be completed by its earliest expected completion date is: A. 50 percent. B. 95 percent. C. 100 percent. D. impossible to determine. 2) If on?handinventory? = 100? units, scheduled receipts? = 200 units and backorders? = 100? units, the Inventory Position? (IP) is 100 units. True or False?
PLEASE INDICATE CORRECT ANSWER ONLY! 1) The probability that a project will be completed by its...
PLEASE INDICATE CORRECT ANSWER ONLY! 1) The probability that a project will be completed by its earliest expected completion date is: A. 50 percent. B. 95 percent. C. 100 percent. D. impossible to determine. 2) If on?handinventory? = 100? units, scheduled receipts? = 200 units and backorders? = 100? units, the Inventory Position? (IP) is 100 units. True or False?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT