Question

At the commencement of a project, a member of a scrum team identifies a potential risk...

At the commencement of a project, a member of a scrum team identifies a potential risk related to the amount of work needed to adapt a particular software package to implement some user stories. These user stories are important to the customer but they are not of the highest priority. This team member suggests that the scrum process should be adapted to account for this risk. What important changes should be made to the scrum process in this case?

Homework Answers

Answer #1

The main changes that have to be implemented in this scrum process are:

  1. A product backlog should be initially created where all the user stories will be categorized based on priority and the dependency of the upcoming work on the current user stories.
  2. The developers should complete the high priority user stories and proceed towards the rest.
  3. The product owner should ensure that the user stories, especially the ones that are important to the customer are completed and delivered to the customer on time with proper testing done to maintain the quality of the project.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
What should be the first step a team should take to feed potential problems into the...
What should be the first step a team should take to feed potential problems into the Problem Solving Workshop? Identify the enablers needed to build out the Architectural Runway Conduct a short term retrospective Analyze quantitative and qualitative metrics Review feedback from System Demo What are the two purposes of the Scrum of Scrums? (choose two) Discuss program backlog priority changes Review solution architecture Facilitate cross team collaboration Collaborate release details with Systems team Identify impediments Why is the program...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Funding an IS project through a Chargeback method involves: Pricing the IS service out for the...
Funding an IS project through a Chargeback method involves: Pricing the IS service out for the customer buying the end product Direct billing by the firm for IS resources or services to the department that uses them Direct billing by the manager of a function for IS resources or services to an employee that uses them An accounting process that reduces tax liability for capital investments All of the following are attributes of considering IS costs as Overhead except the...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....
Explain the complete HAZOP procedure as followed in the industry. See summary below. Explain all the...
Explain the complete HAZOP procedure as followed in the industry. See summary below. Explain all the main parts of HAZOP study in details given in the Pdf file including: 1. Overview (including definitions and usage) 2. Hazop methodology (including phases like definition, preparation, examination, documentation and follow-up). Give examples also 3. Risk review 4. Risk communication Guidance: Study the procedure carefully and then write the answers in your own words. Hazard & Operability Analysis (HAZOP) 1   Overview: Hazard and Operability...
Case Study: Position Description and Specification for an HRIS Administrator One way to assess the nature...
Case Study: Position Description and Specification for an HRIS Administrator One way to assess the nature and importance of a particular function or position in an organization is to examine the job description and job specifications for this position, as they tell us what activities, duties, and tasks are involved in the job as well as what knowledge, skills, and abilities (KSA) are required to perform the job. The following is an actual advertisement for an HRIS administrator. A large...
Case Study: Position Description and Specification for an HRIS Administrator One way to assess the nature...
Case Study: Position Description and Specification for an HRIS Administrator One way to assess the nature and importance of a particular function or position in an organization is to examine the job description and job specifications for this position, as they tell us what activities, duties, and tasks are involved in the job as well as what knowledge, skills, and abilities (KSA) are required to perform the job. The following is an actual advertisement for an HRIS administrator. A large...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT