Designing a bridge foundation on a highly compressible clay deposit with Cv = 2 × 10-5 cm2 /sec. The specifications require that the clay needs to complete 70% of the primary consolidation. Determine: how much time is needed to meet the specifications? The soil deposit is 3.5 m thick and is drained only at the top of the layer.