Before the project manager develops an activity logic network, he/she must ask questions for each activity on the list. What are the 4 questions that must be asked?
To develop logical network we have to know the -
most important questions are
1. Early start time or activity start time
2. Early finish time or activity finish time
3. finish details of previous activity
4. start activity of details later activity
apart from these four there are some more questions.
1. Maximum time taken by activity if all the conditions are unfavorable.
2. Minimum time taken by activity if all the conditons are favorable.
3. how much resources is available for that activity.
4. Dependecy of that activity on other or vica-versa.
5. Priority and functions of that activity i.e. if an acitivty consuming so much time then can we avoid that activity.
6. How much that activity is imortant for the project