Question

Before the project manager develops an activity logic network, he/she must ask questions for each activity...

Before the project manager develops an activity logic network, he/she must ask questions for each activity on the list. What are the 4 questions that must be asked?

Homework Answers

Answer #1

To develop logical network we have to know the -

most important questions are

1. Early start time or activity start time

2. Early finish time or activity finish time

3. finish details of previous activity

4. start activity of details later activity

apart from these four there are some more questions.

1. Maximum time taken by activity if all the conditions are unfavorable.

2. Minimum time taken by activity if all the conditons are favorable.

3. how much resources is available for that activity.

4. Dependecy of that activity on other or vica-versa.

5. Priority and functions of that activity i.e. if an acitivty consuming so much time then can we avoid that activity.

6. How much that activity is imortant for the project

comment for any doubt about this solution thank you

Don't forget to upvote if you got your answer

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
CPM a. is a network technique that allows three time estimates for each activity in a...
CPM a. is a network technique that allows three time estimates for each activity in a project. b. assumes we do not know ahead of time what activities must be completed. c. assumes that activity time estimates follow the normal probability distribution. d. is a deterministic network technique that allows for project crashing.
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What...
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
Sydney was a newly hired project manager at a consulting firm. She has previous experience working...
Sydney was a newly hired project manager at a consulting firm. She has previous experience working on project teams but had never led a project on her own. She has only been with the firm for two weeks and has spent a week of that time in onboarding. Her manager, the head of operations, has just assigned her to a rather large project. The project is to evaluate the current processes in use within the organization specifically focused in two...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Before a person can sit on a jury for a capital punishment case, he or she...
Before a person can sit on a jury for a capital punishment case, he or she must be “death qualified”. This means prospective jurors are asked about their views regarding the death penalty. Those who would automatically vote for the death penalty or those who could not vote for the death penalty for conscience reasons are excused. This has been shown to stack the jury against the defendant because, generally, jurors are for the death penalty. My questions to you...
You are the project manager for an upgrade of computers in your company. You need to...
You are the project manager for an upgrade of computers in your company. You need to upgrade 30 systems, including 10 desktops (for office personnel) and 20 laptops (for remote workers). Each system must access the company network, as well as a common installation of software, security components, and so forth. You must submit your risk identification in a summary that will be used during a presentation for the CIO. In a 3–5 page document, complete the following: Identify four...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT