Question

Your company is bidding on an office building. The estimated construction costs are as follows: Labor...

Your company is bidding on an office building. The estimated construction costs are as follows:

Labor = $985,466

Materials = $1,091,256

Equipment = $100,754

Subcontractor’s bids = $6,254,800

Your company marks up labor and materials 15%, equipment 20%, and subcontractor’s bids 4% to cover main-office overhead and profit. What is your company’s bid for the project?

Homework Answers

Answer #1

Marked up price (M) = A x (1+ P%)

where A = actual cost

P = percentage mark up

Actual Labour Cost = 985466 $

Marked up Labour Cost (L) = 985466x(1+15/100)

= 1133285.9 $

Actual materials Cost = 1091256 $

Marked up materials Cost (M) = 1091256(1+15/100)

= 1254944.4 $

Actual equipment Cost = 100754 $

Marked up equipment Cost (E) = 100754x(1+20/100)

= 120904.8 $

Actual Subcontractor's Bids = 6254800 $

Marked up Subcontractor's Bids (S) = 6254800x(1+4/100)

= 6504992 $

Company's Bid for project = L + M + E + S

= 1133285.9 + 1254944.4 + 120904.8 + 6504992

= 9014127.1 $

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Reliable Construction Company Reliable Construction Company is deciding how much they will bid for a contract...
Reliable Construction Company Reliable Construction Company is deciding how much they will bid for a contract to build a new plant for a major manufacturer. Based on the specifications of the new plant, Reliable has estimated what the company’s total cost would be if it were to undertake the project. Reliable estimates that the project would cost $4.55 million (M) and are thinking about bidding $5.4 M in the proposal. Reliable also estimates that the cost of preparing a proposal...
Reliable Construction Company Reliable Construction Company is deciding how much they will bid for a contract...
Reliable Construction Company Reliable Construction Company is deciding how much they will bid for a contract to build a new plant for a major manufacturer. Based on the specifications of the new plant, Reliable has estimated what the company’s total cost would be if it were to undertake the project. Reliable estimates that the project would cost $4.55 million (M) and are thinking about bidding $5.4 M in the proposal. Reliable also estimates that the cost of preparing a proposal...
Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion....
Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion. At the start of Year 1, Kip enters a contract to build an office building for $100 million. The project is completed by the end of Year 2. The following additional information is available for this project (amounts in millions): YEAR 1 YEAR 2 Costs incurred during each year $20 $70 Costs expected in future $60 0 sallys Year 2 revenue will be:
Given: The Blue Bird Company’s for 2018 paid $35,000,000 in Direct Labor Wages. The company building...
Given: The Blue Bird Company’s for 2018 paid $35,000,000 in Direct Labor Wages. The company building is 150 foot x 150 foot. Building use: 15% for office area and 65% for manufacturing and 20% for warehouse. They employ 7 indirect workers. Various costs for year 2018 follows: Description of Company Costs Cost Fringe Benefits for Direct and Indirect Labor Fringe benefit % = 30% of Labor Costs Salary people payroll NOT including fringes $2,000,000 / year Shop Supplies $200,000 /...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $14,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,800,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,060,000 Long-term loan-11% interest, payable on January 1 of...
During January 2020, the following transactions occurred: 3. Labor was incurred as follows. All labor costs...
During January 2020, the following transactions occurred: 3. Labor was incurred as follows. All labor costs are recorded as Payroll Payable initially, and the liability is reduced when the cash payment is made.                         Direct Labor:                                        Hours            Dollars                                     Job 870                                         150             $2,400                                     Job 871                                         650               9,750                                     Job 872                                       1200             16,200                                     Job 873                                         400               6,200                                                       Job 874                                         350               5,950                         Indirect labor                                                                 9,250                         Marketing and administrative labor                            39,400 4. Manufacturing overhead was applied...
Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use...
Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,000 on January 1, 2017. Harrisburg expected to complete the building by December 31, 2017. Harrisburg has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $2,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,400,000 Long-term loan-11% interest, payable on January 1 of...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2019 $3,400,000 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,380,000 Long-term loan-9% interest, payable on January 1 of...
Splish Furniture Company started construction of a combination office and warehouse building for its own use...
Splish Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Splish expected to complete the building by December 31, 2020. Splish has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,780,000 Long-term loan-11% interest, payable on January 1 of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT